专利摘要:
SUMMARY The invention relates to a method of an HC dosing system comprising a dosing unit (250) for dosing fuel into an engine exhaust duct (290) upstream of a particulate filter (270) for purifying exhaust gases in said engine, wherein said HC dosing system includes pressurizing means (230) for supplying fuel from a container (205) to said dosing unit (250) arranged to dose said fuel under pressure to said exhaust duct (290). The method comprises the step of: - during periods of non-continuous dosing of fuel, during continued maintenance of said pressurizing means (230), lowering the pressure (s301; s320) of said branch at the dosing unit (250) compared with the pressure at continuous dosing. The invention also relates to a computer program product comprising program code (P) for a computer (200; 210) for implementing a method according to the invention. The invention also relates to an HC dosing system and a motor vehicle which is equipped with said HC dosing system.
公开号:SE1350272A1
申请号:SE1350272
申请日:2013-03-07
公开日:2014-09-12
发明作者:Andreas Liljestrand
申请人:Scania Cv Ab;
IPC主号:
专利说明:

TECHNICAL FIELD The present invention relates to a process for an HC dosing system (Hydro Carbon, carbonate) comprising a dosing unit for dosing fuel into an engine exhaust duct. The invention also relates to a computer program product comprising program code for a computer for implementing a method according to the invention. The invention also relates to an HC dosing system and a motor vehicle equipped with the HC dosing system.
BACKGROUND In today's vehicles, e.g. diesel as a fuel in DPF (Diesel Particulate Filter) systems including a particulate filter. The particle filter is arranged to capture e.g. diesel particles and soot. During active regeneration of the particle filter, diesel is fed to an exhaust pipe downstream of an engine, which diesel is led into an oxidation catalyst, also called DOC. In the oxidation catalyst, said diesel is combusted and provides a homing of the temperature of the exhaust system. In this way, active regeneration of the particulate filter arranged downstream of the oxidation catalyst can be achieved.
One type of DPF system includes a container containing diesel. The DPF system also has a pump which is arranged to inflate said diesel Iran container via a suction hose and supply it via a pressurized hose to a dosing unit which is arranged at an exhaust system of the vehicle, such as e.g. at an exhaust pipe of the exhaust system. The container can be the vehicle's fuel tank or a separate container with the DPF system. The dosing unit is arranged to inject a required amount of diesel into the exhaust pipe upstream of the particulate filter according to drivers stored in a control unit of the vehicle. In order to more easily regulate the pressure at small or no dosage amounts, the system also consists of a return hose which is arranged from a pressure side of the system back to the container. The dosing can, for example, take place at a predetermined rate, such as between 1 Hz, where the dosing unit is open during a certain predetermined period of each rate, whereby fueled industry can be dosed. 2 There is a constant need to reduce the amount of emissions from engines of motor vehicles. This applies not least to heavy motor vehicles such as e.g. trucks and buses because legal requirements for alit minor emissions are continuously tightened. It is therefore of the utmost importance that the HC dosing system in vehicles performs a satisfactory function so that performance is not reduced.
In many operational cases in the vehicle, no fuel is dosed in the exhaust system, as active regeneration is not required as often. Such an operating case is when regeneration of the particle filter is not required, since the particle filter is not considered to have a sufficiently high degree of storage. Another such operational case can e.g. be cla the vehicle's exhaust temperature is lower than a certain predetermined temperature. Another such operating case when no dosing takes place may be when a radiating temperature of a surface of or component in of the exhaust duct from the vehicle's engine is lower than a certain predetermined temperature. In this case, the dosed industry cannot be evaporated to any great extent. Leakage of fuel can have a negative effect on a vehicle's finishing system. It should be noted that a finishing system for, for example, heavy vehicles of today accounts for a significant part of the total value of the vehicle.
The dosing unit is thus kept closed in many operating cases so that dosing of fuel is simply not undesirable.
Because the fuel in the HC dosing system is pressurized, unwanted leakage of fuel from the dosing unit to the exhaust duct can occur for various reasons, even during periods when the dosing unit is closed in order not to dose fuel. In the event of adverse conditions, this leakage can cause undesired transient temperature rises in exhaust gases from said engine, which can adversely affect the HC dosing system. This can also have a negative impact on an SCR system having the vehicle.
A problem associated with fuel leakage has the metering unit when dosing should not take place is that this fuel is sometimes not evaporated or burned in a correct manner, this fuel can be stored in catalysts arranged downstream of a metering station of a 3 exhaust duct from an engine. This can adversely affect said catalysts or lead to undesired combustion at the wrong location of the exhaust duct. Unwanted leakage of fuel at the dosing unit can adversely affect a finishing system, including in thermal terms.
It is therefore unreasonable to ensure that no or minimal leakage of fuel occurs when the dosing unit is closed.
SUMMARY OF THE INVENTION An object of the present invention is to provide a new and advantageous method in an HC dosing system for preventing leakage of fuel when a dosing unit of the HC dosing system is closed.
Another object of the invention is to provide a new and advantageous HC dosing system and a new and advantageous computer program with an HC dosing system.
A further object of the invention is to provide a method, an HC dosing system and a computer program in an HC dosing system for achieving improved performance of a motor vehicle.
A further object of the invention is to provide a method, an HC dosing system and a computer program in an HC dosing system for reducing the risk of undesired temperature rises of exhaust gases of an exhaust duct from an engine.
A further object of the invention is to provide a method, an HC dosing system and a computer program in an HC dosing system for reducing the risk of leakage of fuel from a dosing unit for dosing fuel to an exhaust duct to conduct exhaust gases from an engine.
These objects are achieved by a method of an HC dosing system according to claim 1. According to one aspect of the present invention there is provided a method of an HC dosing system comprising a dosing unit for dosing fuel into an engine exhaust duct upstream of a particulate filter for purifying exhaust gases from said engine. , wherein said HC dosing system includes pressurizing means (230) for supplying fuel from a container to said dosing unit arranged to dose pressurize said fuel to said exhaust duct. The method comprises the step of: - during periods of non-continuous dosing of fuel, during continued sustained operation of said pressurizing means, lowering the pressure of said branch at the dosing unit compared with the pressure at continuous dosing.
According to one aspect of the present invention there is provided a method of an HC metering system for purifying exhaust gases from an engine wherein said HC metering system includes pressurizing means for feeding fuel from a container to a metering unit arranged to pressurize said fuel into an exhaust duct, the method comprising the step of during periods of non-continuous dosing of fuel, during operation of said pressurizing means, lowering the pressure of said fuel at the dosing unit compared with the pressure at continuous dosing.
According to an aspect of the invention, the pressurizing means can supply fuel from a container to said dosing unit and thereby pressurize said fuel to a lamp pressure, for example a pressure between 5 and 15 Bar, for example 9 Bar, when dosing said fuel to said exhaust duct. During periods of non-continuous dosing of the industry, the pressure in the industry can be lowered to a higher pressure level in Iran (where dosing takes place continuously) to a lower pressure level, for example a pressure level between 1 and 6 Bar, such as 2 Bar or 5 Bar. According to one example, the pressure in the industry can be reduced from a pressure level of, for example, 50 Bar, when dosing takes place, to a pressure level of, for example, 5 Bar, where continuous dosing does not take place.
By lowering the pressure of the industry at the dosing unit, the risk of leakage of the industry during periods of non-dosing of said industry is reduced. A leakage of fuel can adversely affect the function of the HC dosing system, which can mean that undesirable exhaust gases are emitted from a finishing system of the vehicle. Leakage of fuel in the dosing unit can cause a trafficking surface of the exhaust duct to be adversely affected, which can adversely affect the function of the HC dosing system.
D5 the pressurizing means also during non-dosing and is in operation, it is faster to work up the pressure again to a level dA dosing of the fuel takes place in conjunction with the procedure where the pressurizing means is switched off completely. At the same time, advantageous cooling of the dosing unit by means of a flowing fuel around it can be maintained.
A period of non-continuous dosing of fuel can be a certain predetermined time that is installable. An example of a time interval within which said installable predetermined time is may be between 1 s and 60 s, but other predetermined time periods are also possible.
A period of non-continuous dosing of fuel may involve a certain fixed number of beats (IA dosing does not take place.
According to one aspect of the invention, the pressure of the industry at the dosage unit may be reduced from a first higher pressure level to a lower second pressure level after a predetermined period of non-dosing and then back to said first higher pressure level, or other appropriate higher pressure level, after a predetermined period of dosing.
According to an exemplary embodiment, a pressure of said fuel at the dosing unit can be increased from said lower pressure level to said higher pressure level at a fixed dosing cup. In this case, dosing of the fuel can be resumed (started) at the said pressure at the fuel when the said higher pressure level5.
According to one aspect of the invention, the pressure of the industry at the metering unit can be collected at a certain predetermined pressure drop rate.
According to one aspect of the invention, a period of non-continuous dosing may occur depending on the operating condition of the engine. An operating case where continuous dosing does not occur may be when the exhaust gases from the engine have a temperature below a certain predetermined temperature. Another operating case where continuous dosing does not occur may be when the engine is idling. There are also other operational cases as continuous dosing of fuel does not take place. In a number of operating cases when continuous dosing does not take place, the inventive method can be used.
Dosing of fuel by means of the dosing unit takes place first when the particle filter is to be regenerated.
According to another aspect of the present invention, the pressure of the industry during periods of non-continuous dosing can only be reduced when certain criteria are met. These criteria may, for example, be one or more of the following: the temperature of the exhaust gases is below a certain predetermined value; and / or leakage of the industry of the dosing unit has been detected.
Said lacquer can be fixed in an appropriate manner. According to this aspect and only in cases cla one or more of the above criteria are met sanks pressure during periods of non-dosing of fuel.
The upright operation of the said pressurizing means meant that the pressurizing means is in operation, i.e. it does not close ay.
The pressurizing means may, for example, comprise a pump, such as a diaphragm pump.
The method may comprise the step of: lowering the pressure of said fuel at the metering unit by reducing a speed of said pressurizing means. This provides an effective way of lowering said pressure in an appropriate manner. Said pressurizing means can then be controlled to other said pressures relatively quickly.
According to one aspect of the invention, the pressurizing means is a pump for which the speed can be adjusted to reduce its power and thereby reduce the pressure of the industry at said dosing unit. The method may comprise the step of: - lowering the pressure of said fuel at the dosing unit by reducing a stroke frequency of said pressurizing means. In doing so, an effective way of collecting said pressure is achieved. Said pressurizing means can then be controlled to other said pressures relatively quickly.
According to one aspect of the invention, the pressurizing means is a pump for which the stroke frequency can be adjusted to reduce the power and thereby reduce the pressure of the fuel at the dosing unit.
The method may include the step of: - lowering the pressure of said fuel at the metering unit by controlling a valve configuration of a downstream side of the metering unit. This provides an effective way to reduce said pressure. Said pressurizing means can then be controlled to change said pressure relatively quickly. By increasing a flow of brittleness of the valve configuration, the pressure of the fuel at the dosing unit can be reduced in an efficient manner.
According to one aspect of the invention, the pressure of the industry at the dosing unit is lowered by fully opening said valve configuration located downstream of the dosing unit. At normal pressure, during continuous dosing of fuel, the valve configuration may be closed or only be open to a certain extent. With a pressure drop of the industry, as with non-continuous dosing of industry, the valve configuration can be opened more and the industry can pass more easily through the valve configuration, which means that the pressure of the industry at the dosing unit decreases.
For pressurizing means with a controllable displacement, said control of a pressure of the branch at the dosing unit can be achieved during the maintained speed. That is, according to one embodiment, said pressure changes can be achieved without changing a speed of said pressure protection means. The method may comprise the step of: lowering the pressure of said industry at the dosing unit by directing said industry Iran said pressurizing means to said container past said dosing unit.
According to one aspect, when the pressure is to be collected, the industry can be led past the dosing unit, from the pressurizing means to the container. A valve configuration consisting of one or more valves can, for example, control the flow of fuel, either to the dosing unit or past the dosing unit. Said first control unit may be arranged to control said valve configuration in accordance with the present invention.
The method may comprise the step of: lowering the pressure of said fuel at the dosing unit by controlling a feeding means arranged downstream of the dosing unit.
By placing a feeding means downstream of the dosing unit, the pressure of the industry can be reduced by the feeding means collecting the pressure downstream of the dosing unit.
The supply means may, for example, be a pump such as a diaphragm pump or another type of pump.
The method may comprise the step of substantially lowering the pressure of said fuel at the dosing unit.
The pressure can, for example, be reduced from a level of 9 Bar to a level of 2 Bar. Alternatively, the pressure can be reduced from a level of 9 Bar to a level of 5 Bar. Lowering the pressure significantly can mean that the pressure drops by at least 20% relative to the pressure of the reducing agent during continuous dosing. Reducing the pressure significantly can mean that the pressure drops by at least 40% relative to the pressure in the industry during continuous dosing. Lowering the pressure of the said branch at the dosing unit can significantly mean lowering the pressure by more than 80% relative to the pressure of the branch during continuous dosing.
The process may involve a stepless lowering of the pressure. This stepless lowering of the pressure of the industry can be accomplished by flaking the components which lower the pressure such as: the pressurizing means; a valve configuration downstream of the dosing unit; At least one valve configuration that directs fuel past the dosing unit.
The stepless collection can take place at varying speeds. The speed can vary depending on various parameters such as engine type, etc., and it can also vary during an ongoing reduction of the pressure of the industry.
The process may involve a reduction in the pressure of the industry in steps.
This lowering of the pressure of the industry in steps can be accomplished with one of the components which can effect the lowering of the pressure skarn: the pressurizing means; a valve configuration downstream of the dosing unit; At least one valve configuration that directs fuel past the dosing unit.
The pressure in the industry can be reduced in any number of steps.
The method may comprise the step of: in the case of resumed continuous dosing, raising the pressure of said industry at the dosing unit.
The method may comprise the step of: raising the pressure of said industry at the dosing unit before continuous dosing is resumed or started.
The method may comprise the step of: raising the pressure of said industry at the dosing unit before continuous dosing is resumed or started on the basis of a fixed dosing request.
After a period of non-dosing of the industry, the industry can be dosed again. In this case, the pressure of the branch at the dosing unit is raised again to a suitable pressure level which is set for dosing the branch.
The method may comprise the step of: - at a predetermined time before a fixed time cla continuous dosing of fuel should cease, start pressure reduction of said industry at the dosing unit.
In order for the pressure in the industry to be at a 15g level when the dosing unit is closed, the pressure drop according to an exemplary embodiment can be started a predetermined time before a fixed time when dosing of the industry is to cease.
The procedure is easy to implement in existing motor vehicles. Program code for controlling a pressure drop of a fuel at a dosing unit in an HC dosing system to prevent leakage of fuel c15 the dosing unit is closed, according to an aspect of the invention, can be installed in a control unit of the vehicle during manufacture thereof. A buyer of the vehicle may thus be able to choose the function of the procedure as an option. Alternatively, program code to perform the innovative procedure can be installed in a control unit has the vehicle when upgrading at a service station. In this case, the program mode can be loaded into a memory in the control unit.
Program code for pressure reduction of a fuel at a dosing unit in a HC dosing system to prevent leakage of fuel when the dosing unit is closed can be easily updated or replaced. Furthermore, different parts of the program code can be exchanged independently of each other. This modular configuration is advantageous from an underpass perspective.
According to one aspect of the present invention, there is provided an HC dosing system arranged to dispense fuel into an engine exhaust duct upstream of a particulate filter for purifying exhaust gases from said engine, said HC dosing system comprising: a dosing unit adapted to dispense said fuel to said fuel. exhaust duct; a pressurizing means adapted to supply fuel from a container to said dosing unit; means adapted to, during periods of non-continuous dosing of fuel, during continued upright operation of said pressurizing means, lower the pressure of said fuel at the dosing unit compared with the pressure at continuous dosing. According to one aspect of the invention, there is provided an HC dosing system wherein said pressurizing means comprises a pump with controllable speed. According to one aspect of the invention, there is provided an HC dosing system, said pressurizing means comprising a pump having a controllable stroke frequency. The device may comprise a valve configuration arranged at a downstream side of the dosing unit. The device may comprise means for substantially lowering the pressure of said fuel. The device may comprise means for lowering the pressure of said industry steplessly. The device may comprise means for relieving the pressure of said industry in steps. The device may comprise means for directing said fuel from said pressurizing means to said container past said dosing unit. The device may comprise a feeding means arranged downstream of the dosing unit. The HC dosing system may include a DPF. The HC dosing system may be included in a DPF system. The HC dosing system may comprise a DOC unit arranged upstream of said particulate filter of said exhaust duct from said engine. The fuel can be diesel or other carbonate-based fuel.
The above objects are also achieved with a motor vehicle comprising the HC dosing system according to the invention. The motor vehicle can be a truck, bus or car.
According to one aspect of the invention, there is provided a computer program for pressure lowering a fuel at a metering unit in an HC metering system to prevent leakage of fuel when the metering unit is closed, said computer program comprising program code for causing an electronic controller or other computer connected to it. electronic control unit to perform the steps according to any one of claims 1-11.
According to one aspect of the invention, there is provided a computer program for depressurizing a fuel at a metering unit in an HC metering system to prevent leakage of fuel when the metering unit is closed, said computer program comprising program code stored on a computer readable medium for causing an electronic control unit or another computer connected to the electronic control unit to perform the steps according to any one of claims 1-11. According to one aspect of the invention, there is provided a computer program in an HC dosing system, said computer program comprising program code for causing an electronic controller or another computer connected to the electronic controller to perform the steps of any of claims 1-11.
According to one aspect of the invention, there is provided a computer program in an HC dosing system, said computer program comprising program code stored on a computer readable medium for causing an electronic controller or other computer connected to the electronic controller to perform the steps of any of claims 1. -11.
According to one aspect of the invention, there is provided a computer program product comprising a program code stored on a computer readable medium for performing the method steps of any of claims 1-11, when said program code is crossed on an electronic control unit or another computer connected to the electronic control unit. .
Additional objects, advantages, and novel features of the present invention will become apparent to those skilled in the art from the following details, as well as through the practice of the invention. While the invention is described below, it is to be understood that the invention is not limited to the specific details described. Those skilled in the art having access to the teachings will again appreciate further applications, modifications and incorporations within other fields which are within the scope of the invention.
SUMMARY DESCRIPTION OF THE DRAWINGS For a more complete understanding of the present invention and further objects and advantages thereof, we will now refer to the following detailed description which is to be read in conjunction with the accompanying drawings in which like reference numerals refer to like parts in the various figures, and in which: 1 schematically illustrates a vehicle, according to an embodiment of the invention; Figure 2a schematically illustrates an HC dosing system, according to an embodiment of the invention; Figure 2b schematically illustrates a dosing unit of the HC dosing system; Figure 3a schematically illustrates a flow chart of a process, according to an embodiment of the invention; Figure 3b schematically illustrates in further detail a flow chart of a method, according to an aspect of the invention; Figure 4a schematically illustrates a diagram, according to an aspect of the invention; Figure 4b schematically illustrates a diagram, according to an aspect of the invention; Figure 4c schematically illustrates a diagram, according to an aspect of the invention; Figure 4d schematically illustrates a diagram, according to an aspect of the invention; and Figure 5 schematically illustrates a computer, according to an embodiment of the invention.
DETAILED DESCRIPTION OF THE FIGURES Referring to Figure 1, a side view of a vehicle 100 is shown. The exemplary vehicle 100 consists of a tractor 110 and a trailer 112. The vehicle may be a heavy vehicle, such as a truck or a bus. The vehicle can alternatively be a car. The vehicle may alternatively be a truck, dumper or crane, or other suitable platform including an engine and a HC dosing system.
It should be noted that the invention is suitable for application to any suitable HC dosing system comprising a fuel dosing unit and a particulate filter and is thus not limited to the HC dosing system of motor vehicles. The innovative process for an HC dosing system and the innovative HC dosing system according to an aspect of the invention are suitable for other platforms which include an HC dosing system for motor vehicles, such as e.g. watercraft. The watercraft can be of any suitable type, such as e.g. motorboats, ships, ferries or ships.
The innovative process and the innovative HC dosing system according to an aspect of the invention are also suitable for e.g. systems including, for example, a stone crusher or the like. The innovative method and the innovative HC dosing system according to an aspect of the invention are also suitable for v5I for e.g. systems including industrial engines and / or motorized industrial robots.
The innovative process and the innovative HC dosing system according to an aspect of the invention also provide choices for different types of power plants, e.g. an electric power plant comprising a diesel generator.
The innovative process and the innovative HC dosing system make choices for an arbitrary 15-liter engine system that includes an engine and an HC dosing system with a dosing unit and a particulate filter, e.g. has a locomotive or other platform.
The innovative procedure and the innovative HC dosing system make choices for an arbitrary Compulsory system that includes a NON generator and an HC dosing system with a dosing unit and a particulate filter.
The method according to the invention lends itself to a suitable system which generates exhaust gases with particles and a filter which stores particles, which particles can be consumed in a regeneration of said filter, in particular in an active regeneration of said filter.
It should be noted that the HC dosing system can be any suitable HC dosing system, even if it is exemplified as an HC dosing system in a DPF system having a vehicle. The pressurizing means may be a suitable pressurizing means, and need not be a diaphragm pump which is described herein.
The invention is applicable to industry dosing systems which are arranged to raise a temperature if the exhaust gases from the engine are for other reasons in order to regenerate said particulate filter.
The fuel has the HC dosing system can be a suitable industry, e.g. oil, skom e.g. lubricating oil, diesel or other hydrocarbon-based fuels, such as gasoline, ethanol or methane, etc.
The term "lank" refers to a communication link which may be a physical line, whether an optoelectronic communication line, or a non-physical line, such as a wireless connection, for example a radio or microwave line.
In this he uses the term "line" to a passage to hold and transport a fluid, e.g. a branch in liquid form. The wire can be a root of any dimension. The cable can consist of an arbitrary, suitable material, such as e.g. plastic, rubber or metal.
The term "fuel" refers to an agent used for the active regeneration of a particulate filter in an HC dosing system. The said industry is according to a performing diesel. Of course, other types of carbonate based industries can be used. Diesel is mentioned as an example of an industry, but a person skilled in the art realizes that the innovative method and the innovative device can be realized for other types of industry, with the necessary adaptations, such as e.g. adjustments to adequate boiling temperature for selected industries, in control algorithms to execute program code in accordance with the innovative procedure.
Although the term HC dosing system is used herein to indicate a particulate filter system, the invention is not limited to the use of a diesel particulate filter. On the contrary, other types of particle filters can be used according to the invention. One skilled in the art will recognize what kind of industry the bast lamps are for regenerating the selected particulate filter.
Referring to Figure 2a, an HC dosing system 299 of the vehicle 100 is shown. The HC dosing system 299 may be provided in the tractor 110. According to this example, the HC dosing system 299 comprises a container 205 which is arranged to hold a branch. The container 205 is arranged to contain a suitable amount of fuel and is also arranged to be able to be refilled if necessary.
A first line 271 is arranged to direct the fuel to a pump 230 from the container 205.
The pump 230 may also be referred to as the pressurizing means. The pump 230 can be a suitable pump. The pump 230 may be a diaphragm pump comprising at least one filter. The pump 16 230 can be arranged to be operated by means of an electric motor (not shown). The pump 230 may be arranged to pump up the fuel Iran the container 205 via the first line 271 and via a second line 272 supply said fuel to a dosing unit 250. The dosing unit 250 may comprise an electrically controlled dosing device, by means of which a flow of fuel added to the exhaust system can controlled. The pump 230 is arranged to pressurize the fuel in the second line 272. The dosing unit 250 is arranged with a throttling unit, which can also be called throttling valve, against which said pressure has the fuel can be built up in the device 299. The throttling unit is further described with reference to Figure 2b.
The dosing unit 250 is arranged to supply said fuel to an exhaust duct 290 of the vehicle 100. More specifically, the dosing unit 250 is arranged to supply in a controlled manner a suitable amount of fuel to an exhaust duct 290 of the vehicle 100. According to this embodiment, a diesel particulate filter (DPF) 270 arranged downstream of a layer of the exhaust system where the supply of fuel takes place. Said diesel particulate filter can also be called a DPF unit. The amount of fuel supplied to the exhaust system is intended to be combusted in an oxidation catalyst 269, which is arranged upstream of said diesel particulate filter 270 of the exhaust duct 290.
The dosing unit 250 may be arranged at said exhaust duct 290 which is arranged to direct exhaust gases from an internal combustion engine (not shown) of the vehicle 100 to said and further to said diesel particulate filter 270 and further to an environment of the vehicle.
According to one example, a precatalyst is mounted in series with the particulate filter 270. In this case, said precatalyst is arranged upstream of said particulate filter 270.
A third conduit 273 is provided disposed between the metering unit 250 and the container 205. The third conduit 273 is arranged to return non-metered fuel fed to the metering unit 250 to the container 205.
A fourth conduit 274 arranged to direct the fuel between the pump 230 and the container 20 past the dosing unit 250 may, according to one embodiment, be included in the HC dosing system. The first control unit 200 may be signal connected to a valve configuration (not shown) of the fourth line 274. The first control unit 200 may then be adapted to control the line of the fuel from the pump 230 or the second line 272 directly to the container 205 without the industry passing dosing unit 205. In this case, the pressure at the dosing unit 250 can be reduced in a suitable manner according to an aspect of the invention.
The first control unit 200 is arranged for communication with the pump 230 via a long L230. The first control unit 200 is arranged to control operation of the pump 230. According to one example, the first control unit 200 is arranged to control the pump 230 by means of an electric motor (not shown). The first control unit 200 is arranged to control a pressure P of the branch in the second line 272. This can be done in various suitable ways. According to one example, the first control unit 200 is arranged to control a radiating speed RPM of the pump 230. In this case, the pressure can be changed in the opposite way. By increasing the speed of the pump 230, the pressure P can be increased. By lowering the speed of the pump 230, the pressure P can be lowered. According to another example, the first control unit 200 is arranged to second a stroke of the pump 230.
By increasing the stroke of the pump 230, the pressure P can be increased. By reducing the stroke of the pump, the pressure P can be reduced. According to another example, the first control unit 200 is arranged to second a stroke frequency of the pump 230. By increasing the stroke frequency of the pump 230, the pressure P 6 can be increased. By reducing the stroke frequency of the pump 230, the pressure P can be reduced.
A second pump 300 may, according to one embodiment, be included in the HC dosing system. Said second pump 300 may also be referred to as feeding means or feeding means. The first control unit 200 is arranged for communication with the pump 300 via a long L300. The first control unit 200 is arranged to control operation of the pump 300. According to one example, the first control unit 200 is arranged to control the pump 300 by means of an electric motor (not shown). By controlling the pump 300 to reduce a pressure of the branch of an upstream side of the pump 300, the pressure of the branch in the line 272 can be reduced.
The first control unit 200 is arranged for communication with the dosing unit 2 and said throttling unit, which may be included in the dosing unit 250. By controlling the throttling unit, the pressure in the line 272 can be controlled. By reducing the opening in the choke unit, the pressure P in the line 272 can be increased and by enlarging the opening in the choke unit, the pressure P in the line 272 can be reduced.
The first control unit 200 is arranged that during periods of non-continuous dosing of fuel, during continued sustained operation of said pressurizing means 230, the pressure of said branch at said dosing unit 250 compares with the pressure at continuous dosing. The first control unit 200 is arranged to lower the pressure of said branch at the dosing unit 250 by reducing the speed of said pressurizing means 230. The first control unit 200 is arranged to lower the pressure of said branch at the dosing unit 250 by reducing a stroke frequency of said pressurizing means 230. the first control unit 200 is arranged to lower the pressure of said branch at the dosing unit 250 by controlling a valve configuration (not shown) of a downstream side of the dosing unit 250.
The first control unit 200 is arranged to lower the pressure of said fuel at the dosing unit 250 by directing the line of said fuel Iran said pressurizing means 230 to said container 205 past said dosing unit 250. The fuel is passed past said dosing unit via line 274.
The first control unit 200 is arranged to lower the pressure of said branch at the dosing unit 250 by controlling feed means 300 arranged downstream of the dosing unit 250. The first control unit 200 is arranged to lower the pressure of said branch at the dosing unit substantially. The first control unit 200 is arranged to lower the pressure of said industry steplessly. The first control unit 200 is arranged to lower the pressure of said industry in steps. The first control unit 200 may be arranged to raise the pressure of said branch at the dosing unit 250 during resumed continuous dosing. The first control unit 200 may be arranged to raise the pressure to an appropriate level of said fuel at the dosing unit 250 before continuous dosing is started on the basis of a dosing request. Said request can be determined by a suitable system of, for example, the vehicle 100. The first control unit 200 is arranged that at a predetermined time before a fixed time when continuous dosing of fuel is to cease, to start a pressure drop in said branch at the dosing unit 250. arranged for communication with the dosing unit 250 via a long L250. The first control unit 200 is arranged to control the operation of the dosing unit 250 in order to e.g. regulate the supply of fuel to the exhaust system of the vehicle 100.
A second control unit 210 is arranged for communication with the first control unit 200 via a long L210. The second control unit 210 may be releasably connected to the first control unit 200. The second control unit 210 may be a control unit external to the vehicle 100. The second control unit 210 may be arranged to perform the inventive method steps according to the invention. The second control unit 210 can be used to upload program code to the first control unit 200, in particular program code for carrying out the inventive method. The second control unit 210 may alternatively be arranged for communication with the first control unit 200 via an internal network in the vehicle. The second control unit 210 may be arranged to perform substantially similar functions as the first control unit 200, such as e.g. that during non-continuous dosing of fuel of the HC dosing system, during continued maintenance operation of said pressurizing means, lower the pressure of said fuel at the dosing unit compared with the pressure at continuous dosing.
The first control unit 200 is arranged for communication with a first temperature sensor 240 via a long L240. The temperature sensor 240 is arranged to detect a radiating temperature Ti of an exhaust stream from the vehicle's engine. According to one example, the first temperature sensor 240 is arranged at said exhaust duct 290 directly downstream of the vehicle upstream dosing unit 250. The temperature sensor 240 may be arranged in a suitable place having said exhaust duct 290. The first temperature sensor 2 is arranged to continuously detect a radiating temperature Tempi of send signals including information cm said radiating temperature Tempi via line L240 to the first control unit 200.
The first control unit 200 is arranged for communication with a second temperature sensor 260 via a long L260. The second temperature sensor 260 may be arranged to detect a radiating temperature Temp2 of a surface in the exhaust system where the fuel evaporates. The second temperature sensor 260 may be arranged to detect a radiating temperature Temp2 of the exhaust duct 290 in a suitable place. The second temperature sensor 260 may be arranged to detect a radiating temperature Temp2 of a suitable surface or component of the exhaust duct 290. According to one example, the second temperature sensor 260 is arranged at the exhaust duct 290 upstream of the dosing unit 250. According to one example, the second temperature sensor 260 is arranged in the exhaust duct. 290 upstream of the dosing unit 250. According to another example, the second temperature sensor 260 is arranged in an evaporator unit (not shown) or an SCR catalyst (not shown) downstream of the particle filter 270. The second temperature sensor 260 is arranged to continuously detect a radiating temperature Temp2 of a surface or a component of the exhaust duct 290 and send signals including information about said radiating temperature Temp2 via line L260 to the first control unit 200.
According to one embodiment, there is a temperature sensor arranged between the oxidation catalyst 269 and the particle filter 270. This temperature sensor is used to enable monitoring / detection of temperature courses of the oxidation catalyst 269.
According to one embodiment, the first control unit 200 and / or the second control unit 2 are arranged to calculate said first temperature Tempt. This can be done by means of a stored calculation model. The first control unit 200 and / or the second control unit 210 may be arranged to calculate said first temperature Temple on the basis of, for example, a radiating exhaust mass flow, radiating speed of the engine and radiating load of the engine.
According to one embodiment, the first control unit 200 and / or the second control unit 2 are arranged to calculate said second temperature Temp2. This can be done by means of a stored calculation model. The first control unit 200 and / or the second control unit 210 may be arranged to calculate said second temperature Temp2 on the basis of, for example, a radiating exhaust mass flow, radiating speed of the engine and radiating load of the engine.
A first NOx sensor 255 is provided for communication with the first control unit 200 via a long L255. The first NOx sensor 255 is arranged to continuously determine a 21 NO NO content of the exhaust stream upstream of said SCR catalyst, for example upstream of said particle filter 270. According to an example, the first NOx sensor 255 is arranged at the exhaust duct 290 upstream of said dosage unit. 250. The first NOR sensor 255 is arranged to continuously send signals including information about a current NO 1 content upstream of said SCR catalyst to the first control unit 200.
A second NO 1 sensor 265 is provided for communication with the first control unit 200 via a long L265. The second NO sensor 265 is arranged to continuously determine a current NO 2 content of the exhaust gas stream downstream of said SCR catalyst. The second NOR sensor 265 is arranged to continuously send signals including information about a current NO 1 content downstream of said SCR catalyst to the first control unit 200.
According to one embodiment, the first control unit 200 and / or the second control unit 210 are arranged to calculate said first NO, content upstream of said SCR catalyst. This can be done by means of a stored calculation model. The first control unit 200 and / or the second control unit 210 may be arranged to calculate the first NO, content on the basis of, for example, an exhaust gas mass flow, an engine engine speed and an engine load load.
The first control unit 200 is arranged to determine a degree of NO conversion on the basis of said calculated or measured NO, content upstream of said SCR catalyst and said measured NON content downstream of said SCR catalyst.
The first control unit 200 is arranged to continuously control the operation of the HC dosing system 299 on the basis of said first temperature Tempi and / or said second temperature Temp2.
The first control unit 200 is arranged for communication with a pressure sensor 279 via a long L279. The pressure sensor 279 is arranged to detect a moving pressure P of the branch of the second line 272. According to an example, the pressure sensor 271 is arranged of said dosing unit 250 to detect a pressure P of the branch at the dosing unit 250.
The pressure sensor 271 may be arranged in a suitable place to supply a pressure of the fuel at the dosing unit 250. The pressure sensor 271 is arranged to continuously detect a pressure P in the industry and send signals containing information about said smoke pressure P via the line L271 to the first the control unit 200.
According to one embodiment, the first control unit 200 and / or the second control unit 2 are arranged to calculate said pressure P of the industry at said dosing unit 250. This can be done by means of a stored calculation model. The first control unit 200 and / or the second control unit 210 may be arranged to calculate the said pressure P on the basis of, for example, a rated speed of the pump 230 and / or installations of the valve configuration 288 and / or speeds of the pump 300 and / or installations of valve means of said fourth 10 conduit 274.
The first control unit 200 is arranged to continuously determine a smoke degree of clogging of said particle filter 270. This can be done in a suitable manner. The first control unit 200 is arranged to continuously control the operation of the HC dosing system 299 on a basis of the said degree of clogging. In this case, it can be decided, for example, whether, and in this case nk, an active regeneration of said particle filter 270 is to be initiated. The first control unit 200 is arranged to control a regeneration process of said particulate filter 270, for example by continuously dosing said fuel to achieve the required temperature rise of exhaust gases in said exhaust duct 290. These dosing can take place at a suitable pressure P, for example 9 Bar. In the case of non-dosing, said pressure P is controlled to a lower pressure, for example 2 Bar, according to an aspect of the present invention.
The first control unit 200 is arranged to control at least one SCR system of the vehicle IDA base of said NON content upstream of said SCR catalyst and / or said NOR content downstream of said SCR catalyst.
The first control unit 200 is arranged to continuously control the operation of the HC dosing system 299 on the basis of said pressure P of the silicon of the dosing unit 250.
Figure 2b schematically shows the dosing unit 250. The dosing unit 250 comprises a wall 252 with a sate 253 and an elongated device 251. Said device 251 may be a pin or a 23 pin. Said device 251 is slidably arranged. Said device 251 is arranged to be displaced by means of lamp equipment, for example an electromagnetic equipment, in a reciprocating motion marked in Figure 2b in the form of a bidirectional arrow R. Said device 251 is displaceably arranged between two OndlOgen. In a first breath, as shown in Figure 2h, one end of the device abuts substantially against a sate 253, the dosing unit 250 being closed and no dosing taking place. In a second breath, one spirit of the device does not abut said sate 253, whereby the dosing unit 250 is open and dosing can take place.
Bransle is arranged to be led to the dosing unit 250 via the line 272 under pressure. When dosing the fuel, the device is moved in an upward direction, which means that the fuel can pass out through a passage 254 to the exhaust duct 290. In the case of continuous dosing, the device 251 can be retained for a predetermined period of time at a certain rate at said other water layers. into the exhaust duct 290 and for a certain period of time at a certain rate the device 251 can be retained in said first breath, and thereby abut against said sate 253, so that fuel is not dosed into the exhaust duct 290.
Although the device 251 is in said first abutment, abutting the set 253, a certain leakage of fuel can occur between the device 251 and the set 253, in particular under a relatively high pressure P of said branch at the dosing unit 250. The inventive method, where said pressure has said industry is reduced as dosing should not take place, thereby advantageously said coating decreases.
Fuel is supplied to the dosing unit 250 via the passage 272. Fuel that is not dosed is fed from the dosing unit 250 to said container 205 via the line 273. A river direction for said non-dosed fuel is shown by arrows F in Figure 2b.
The first control unit 200 is arranged for communication with a valve configuration 288 via a long L288. Said first control unit 200 is arranged to control the valve configuration 288 and can thereby set an opening degree of said valve configuration 288. By controlling the valve configuration 288 to an at least partially open body, the pressure P of said branch of the dosing unit 250 can be reduced, according to an aspect of the present invention. . By controlling the valve configuration 288 to an at least partially open layer, at the same time as said pressurizing means 230 controls a pressure drop of the branch, the pressure P of the branch of the dosing unit 250 can advantageously be lowered relatively quickly. According to one aspect of the present invention, thus, beneficial synergy effects can be achieved. It was pointed out that the pressure of the branch of the dosing unit 250 can be increased by directing the valve configuration against a rod bearing.
Said dosing unit 250 can be designed according to alternative embodiments. Dosage control by means of said device 251 is only an exemplary embodiment. Other dosage configurations are realizable. According to one example, a displaceable plate, which thanks to said passage 254, may be provided for dosing fuel in a similar manner.
Figure 3a schematically illustrates a flow chart of a process in an HC dosing system comprising a dosing unit 250 for dosing fuel into an engine exhaust duct 290 upstream of a particulate filter 270 for purifying exhaust gases from said engine, said HC dosing system including pressurizing means 230 for feeding fuel Iran a container 205 to said dosing unit 250 arranged to dose under pressure said fuel to said exhaust duct 290. The method includes a first method step s301. The process step s301 comprises the step of: - during periods of non-continuous dosing of fuel, during continued sustained operation of said pressurizing means 230, lowering the pressure of said branch at the dosing unit compared with the pressure at continuous dosing.
After step s301, the procedure is terminated.
Figure 3b schematically illustrates a flow chart of a process in an HC dosing system comprising a dosing unit 250 for dosing fuel into an engine exhaust duct 290 upstream of a particulate filter 270 for purifying exhaust gases from said engine, said HC dosing system including pressurizing means 230 for feeding fuel from a container 205 to said dosing unit 250 arranged to dose said fuel under pressure to said exhaust duct 290, according to an aspect of the present invention.
The process comprises a process step s305. The process step s305 comprises the step of continuously dosing fuel by means of said dosing unit 250 to said exhaust duct 209. Dosing can then take place at a pressure P1, for example 9 Bar. After the process step s305, a subsequent step s310 is performed.
The method step s310 may include the step of activating the inventive method. Named activation can take place automatically. Said activation can take place clA the first control unit 200 determines that said continuous dosing of fuel must be interrupted. Said activation can alternatively take place when the first control unit 200 determines that said continuous dosing of fuel has been interrupted.
The process step s310 may include the step of determining a need to lower the pressure of the industry. Said need to lower the pressure of the industry can be determined by including one or more of the following steps: an operating condition of said engine is checked; time elapsed from the start of non-continuous dosing is recorded; an exhaust gas temperature and / or temperature of a suitable surface or component of said exhaust duct 290 is detected; - an exhaust gas flow is detected.
After the procedure step s310, a subsequent procedure step s320 is performed.
The process step s320 comprises the step of lowering the pressure P in the industry under predetermined operating conditions of said HC dosing system. Said lowering may include a lowering from a pressure P1 to a pressure P2, as described with reference to, for example, Figures 4a-4d. Said predetermined operating conditions may include that dosing of industry should cease or have ceased. Said operating conditions can be determined on the basis of said steps as exemplified in process step s310, for example by comparison with criteria stored in the first control unit 200. Step s320 may include lowering said pressure by: 26 reducing a radiating speed RPM of the pressurizing means 230; reducing a stroke frequency of the pressurizing means 230; or controlling a valve configuration 288 of a downstream side of the metering unit 250; and / or - directing fuel from the pressurizing means 230 to the container 205 past the dosing unit 250; and / or controlling an additional pressurizing means 300 arranged downstream of the dosing unit 250.
The process s320 may involve the step of substantially lowering the pressure of the industry. Method s320 may include the step of lowering the pressure of the industry steplessly. Method s320 may alternatively include the step of lowering the pressure of the industry in steps.
After the procedure step s320, a subsequent procedure step s330 is performed.
The method step s330 may include the step of determining if a degree of storage of the particulate filter 270 is less than a predetermined value. If not, there may be a need to start fueling dosing again.
The process step s330 may include the step of determining the need to increase the pressure of the industry. During re-dosing of the fuel, the pressure of the fuel in line 272 at the dosing unit 250 Ater must be increased to obtain a correct dosing of fuel in the exhaust duct. Alternatively, said needs can be determined on the basis of a request to start continuous dosing of fuel. After step s330, a subsequent step s340 is performed.
The process step s340 involves, if the need is determined, starting dosing of fuel from the dosing unit 250 to the exhaust duct 290 and thereby again raising the pressure P pA suitably, for example from a pressure P2 to a pressure P1. Alternatively, the pressure P can be increased in a suitable manner, for example from a pressure P2 to a pressure P1, after which dosing of fuel from the dosing unit 250 to the exhaust duct 290 is started. After the process step s340, the inventive process is completed. Referring to Figure 4a, a diagram is shown in which the pressure P of the branch at the dosing unit 250 is indicated as a function of time T. The pressure P can be supplied by said pressure sensor 279. Alternatively, the pressure P can be calculated by means of the first control unit 200 in a suitable manner. At a time TWO rod dosing of the branch ay. At a time T1, a pressure drop in the industry at the dosing unit is initiated from a first predetermined pressure level P1 to a second predetermined pressure level P2. The time Ti occurs at a certain predetermined time period after TO. This time period can be an appropriate time period, for example 2 seconds. Figure 4a shows an example where the pressure drop takes place steplessly. At a certain time period after T1, at a time 12, the pressure P night has the second predetermined level P2. The predetermined time period between time Ti and time 12, and thus the pressure drop speed, may, for example, depend on various operating factors of the vehicle. The first pressure level P1 can, for example, be 9 Bar. The second pressure level P2 can be, for example, 2 Bar. The time period between the times T1 and T2 can be, for example, 5 seconds. When initiating dosing of fuel by means of the dosing unit 250, the pressure P can be controlled to a suitable pressure level, for example to said first pressure level P1, in a suitable manner, for example stepless.
According to an exemplary embodiment, said pressure P1 where applicable can be lowered directly to said pressure P2. According to an exemplary embodiment, said pressure P2, where applicable, can be applied directly to said pressure P1.
Referring to Figure 4b, a diagram is shown in which the pressure P of the branch at the dosing unit 250 is indicated as a function of the time T. The pressure P can be supplied by said pressure sensor 279. Alternatively, the pressure P can be calculated by the first control unit 200 in a suitable manner. At a time TWO rod dosing of the branch ay. At a time T1, the pressure drop of the industry at the dosing unit 250 is initiated from a first predetermined pressure level P1 to a second predetermined pressure level P2. The time Ti occurs at a certain predetermined time period after TO. This time period can be an appropriate time period, for example 2 seconds. Figure 4b illustrates an embodiment where the pressure drop takes place in an appropriate number of steps, for example 5 steps. Said steps can be on board different sizes. Said steps can be on board the same size. At a certain time period after Ti, at a time 12, the pressure P night has the second predetermined level P2. The 28 predetermined time period between time Ti and time 12, as well as the steps in which the pressure drop takes place, may depend on different operating factors of the vehicle. The first pressure level P1 can, for example, be 9 Bar. The second pressure level P2 can be, for example, 2 Bar. The time period between the times T1 and T2 can be, for example, 5 seconds. A step can be, for example, 1 or 2 Bar. When initiating dosing of fuel by means of the dosing unit 250, the pressure P can be controlled to a suitable pressure level, for example to said first pressure level P1, in a suitable manner, for example stepless.
Referring to Figure 4c, a diagram is shown in which the pressure P of the branch at the dosing unit 250 is indicated as a function of the time T. The pressure P can be supplied by said pressure sensor 279. Alternatively, the pressure P can be calculated by the first control unit 200 in a suitable manner. At a time TWO rod dosing of the branch ay. At a time Ti, a pressure drop in the industry at the dosing unit 250 is initiated from a first predetermined pressure level P1 to a predetermined pressure level PX. The time Ti occurs at a certain predetermined time period after TO. This time period can be an appropriate time period, for example 5 seconds. Figure 4c illustrates an embodiment where the pressure drop takes place in two steps. At a certain time period after Ti, a pressure drop is initiated when the pressure drops steplessly from said first predetermined pressure level P1 to said pressure level PX. The pressure P reaches said pressure level PX at a second time T2. The time T2 occurs at a certain predetermined time period after the time 11. This time period can be an appropriate time period, for example 2 seconds. The predetermined time period between time Ti and time 12, and thus the pressure drop speed, may, for example, depend on various operating factors of the vehicle. In this case, the said pressure level PX is maintained at a predetermined time T3. At said time T3 a second stepless pressure drop is initiated from said pressure level PX to a second pressure level P2. The pressure P reaches said second pressure level P2 at a fourth time 14. The time T4 occurs at a certain predetermined time period after the time T3. This time period can be an appropriate time period, for example 3 seconds. The predetermined time period between time T3 and time T4, and thus the pressure drop rate, may, for example, depend on various operating factors of the vehicle. The first pressure level P1 can, for example, be Bar. The second pressure level P2 can be, for example, 2Bar. The pressure level PX can be, for example, Bar. When initiating dosing of fuel by means of the dosing unit 250, the pressure P 29 can be controlled to a suitable pressure level, for example to said first pressure level P1, p5 suitably set, for example stepless.
By first controlling the pressure P from said level P1 to said level PX, and thereby waiting for a certain period of time, an advantageous possibility is obtained for evaluation and choice as to whether a further pressure drop from level PX to said level P2 is to be carried out or not. In the event that a further pressure drop from the level PX is not required, at the start of dosing, a pressure increase to said level P1 can be achieved relatively quickly, compared with a pressure increase in the pressure level P2 to the pressure level P1.
Referring to Figure 4d, a diagram shows the valley pressure P of the industry at the dosing unit 250 is given as a function of time T. The pressure P can be measured by said pressure sensor 279. Alternatively, the pressure P can be calculated by means of the first control unit 200. At time TWO rod dosing of the fuel ay. At a time Ti, a pressure drop in the industry at the dosing unit 250 is initiated from a first predetermined pressure level P1 to a pressure level PX. The time Ti occurs at a certain predetermined time period after TO. This time period can be an appropriate time period, for example 3 seconds. Figure 4c illustrates an embodiment in which the pressure reduction takes place in two steps. At a certain time period after Ti, a pressure drop is initiated (IA the pressure drops to said level PX. At time T2, which occurs a certain fee-determined time period after Ti, for example 10 seconds, a second pressure drop is initiated from the pressure level PX to a second pressure level P2. the first pressure level P1 can be, for example, 15 Bar. The second pressure level P2 can be, for example, 5 Bar. The pressure level PX can be, for example, 10 Bar. In this case, said pressure drops are made substantially instantaneously. pressure level, for example to said first pressure level 5 P1, p5 is suitably set, for example stepless.
It should be noted that pressure reduction of the fuel at the dosing unit 250 according to certain embodiments only takes place under predetermined criteria. These criteria may be, for example, one or more of the following: the temperature of a suitable surface has or component i of the exhaust duct 290 or of the exhaust gases in exhaust duct 290 is below a certain predetermined value, for example 200 degrees Celsius; Lack of fuel has the dosing unit 250 has been detected; regeneration of the particle filter 270 is not required; regeneration of the particle filter 270 is not active.
Referring to Figure 5, there is shown a diagram of an embodiment of a device 500. The controllers 200 and 210 described with reference to Figure 2 may in one embodiment include the device 500. The device 500 includes a non-volatile memory 520, a data processing unit 510, and a read / write memory 550. The non-volatile memory 520 has a first memory portion 530 used in a computer program, such as an operating system, stored to control the operation of the device 500. Furthermore, the device 500 comprises a bus controller, a serial communication port, I / O means, an A / D converter, a time and date input and transfer unit, a trade calculator and an interrupt controller (not shown). The non-volatile memory 520 also has a second memory portion 540.
A computer program P is provided which may include routines for depressurizing a fuel at a metering unit in an HC metering system to prevent leakage of fuel (the metering unit is closed. The computer program P may include routines for during periods of non-continuous metering of fuel). while continuing to maintain said pressurizing means 230, the pressure P has said branch at the metering unit 250 as well as the pressure at continuous dosing.The computer program P may include routines for lowering the pressure P has said branch at the metering unit 2 by reducing the speed of said pressurizing means 230. The computer program P may include routines for lowering the pressure having said branch at the metering unit 250 by reducing the stroke frequency having said pressurizing means 230. The computer program P may include routines for lowering the pressure having said branch at the metering unit 250 by controlling a valve configuration 288 having a down The computer program P may include routines for lowering the pressure of the said branch at the dosing unit 250 by directing said branch of said branch from said pressurizing means 230 to said container 205 past said 31 dosing unit 250. Said control may include controlling at least one valve configuration. (not shown) has, for example, said line 274. The fuel can then be led past said dosing unit via said line 274. The computer program P may include routines for lowering the pressure of said branch at the dosing unit by controlling a feed means 300 arranged downstream of the dosing unit 250. The computer program P may include routines for substantially lowering the pressure of said industry at the dosing unit. The computer program P may include routines for reducing the pressure of the said industry steplessly. The computer program P may include routines for lowering the pressure of said industry in steps. The computer program P may comprise routines for raising the pressure of said branch at the dosing unit 250 when resuming continuous dosing. The computer program P may include routines for, at a predetermined time before a fixed time when continuous dosing of branch should cease, to start pressure drop in said branch. dosage unit 250.
The program P can be stored in an executable manner or in a compressed manner in a memory 560 and / or in a read / write memory 550.
When it is described that the data processing unit 510 performs a certain function, it should be understood that the data processing unit 510 performs a certain part of the program which is stored in the memory 560, or a certain part of the program which is stored in the read / write memory 550.
The data processing device 510 can communicate with a data port 599 via a data bus 515. The non-volatile memory 520 is intended for communication with the data processing unit 510 via a data bus 512. The separate memory 560 is intended to communicate with the data processing unit 510 via a data bus 511. Read / write memory 5 is arranged to communicate with the data processing unit 510 via a data bus 514. To the data port 599, e.g. the lanes L210, L230, L240, L250, L255, L260, L265, L279, L288 and L300 are connected (see Figure 2a and Figure 2b).
When data is received on the data port 599, it is temporarily stored in the second memory part 540.
Once the received input data has been temporarily stored, the data processing unit 510 is ready to perform code execution in a manner described above. According to one embodiment, signals received p5 the data port 599 comprise information about an erasing pressure P of the industry at said dosing unit 250. According to one embodiment, signals received p5 the data port 599 include information cm a corrosive temperature of a suitable surface of or component i of the exhaust duct 290 and / or a radiating temperature of the exhaust gases in said exhaust duct 290.
The received signals at the data port 599 can be used by the device 500 to lower the pressure of a fuel at the metering unit 250 in an HC metering system to prevent leakage of the fuel when the metering unit is closed.
Parts of the methods described herein may be performed by the device 500 by means of the data processing unit 510 which the cat program stored in the memory 560 or the read / write memory 550. When the device 500 is the program, the methods described herein are executed.
The foregoing description of the preferred embodiments of the present invention has been provided for the purpose of illustrating and describing the invention. It is not intended to be exhaustive or to limit the invention to the variations described. Obviously, many modifications and variations will occur to those skilled in the art.
The embodiments were chosen and described in order to best explain the principles of the invention and its practical applications, and thus it will be possible for a person skilled in the art to understand the invention for different embodiments and with the various modifications which are suitable for the intended use. 33
权利要求:
Claims (24)
[1]
A method of an HC dosing system comprising a dosing unit (250) for dosing fuel into an engine exhaust duct (290) upstream of a particulate filter (270) for purifying exhaust gases from said engine, said HC dosing system including pressurizing means (230) for feeding fuel from a container (205) to said dosing unit (250) arranged to dose said fuel under pressure to said exhaust duct (290), characterized by the step of: - during periods of non-continuous dosing of fuel, during continued maintenance of said pressurizing means (230), lowering the pressure (s301; s320) of said branch at the dosing unit (250) compared with the pressure at continuous dosing.
[2]
The method of claim 1, comprising the step of: - lowering the pressure (s320) of said fuel at the metering unit (250) by reducing a speed (RPM) of said pressurizing means (230).
[3]
A method according to claim 1, comprising the step of: - lowering the pressure (s320) of said branch at the dosing unit (230) by reducing a stroke frequency of said pressurizing means (230).
[4]
A method according to any one of claims 1-3, comprising the step of: - lowering the pressure (s320) of said branch at the dosing unit (250) by controlling a valve configuration (288) of a downstream side of the dosing unit (250).
[5]
A method according to any one of claims 1-4, comprising the step of: 34 lowering the pressure (s320) of said branch at the dosing unit (250) by directing said branch from said pressurizing means (230) to said container (205) past said dosage unit (250).
[6]
A method according to any one of claims 1-4, comprising the step of: 1. lowering the pressure (s230) of said branch at the dosing unit (250) by controlling a feed means (300) arranged downstream of said dosing unit (250).
[7]
A method according to any one of claims 1-4, comprising the step of: - substantially lowering the pressure (s320) of said fuel at the dosing unit (250).
[8]
A method according to any one of claims 1-7, wherein said lowering of the pressure of said fuel at the dosing unit (250) takes place steplessly.
[9]
A method according to any one of claims 1-7, wherein said lowering of the pressure of said fuel at the dosing unit (250) takes place in steps.
[10]
A method according to any one of the preceding claims, comprising the step of: 1. in the case of resumed continuous dosing, raising the pressure (s340) has the said branch at the dosing unit (250).
[11]
A method according to any one of claims 1-10, comprising the step of: 1. at a predetermined time before a fixed time cla continuous dosing of fuel is to cease, start pressure reduction of said branch at the dosing unit (250).
[12]
HC dosing system arranged to dose fuel into an engine exhaust duct (290) upstream of a particulate filter (270) for purifying exhaust gases from said engine, said HC dosing system comprising: - a dosing unit (250) adapted to dose said pressure under pressure. fuel for said exhaust duct (290); - a pressurizing means (230) adapted to feed fuel from a container (205) to said dosing unit (250), a net sign of: - means (200; 210; 500) adapted to, during periods of non-continuous dosing of fuel, during continued maintenance of operation of said pressurizing means (230), lowering the pressure of said branch at the dosing unit (250) compared with the pressure at continuous dosing.
[13]
The HC dosing system of claim 12, wherein said pressurizing means (230) comprises a controllable speed (RPM) pump.
[14]
The HC dosing system of claim 12, wherein said pressurizing means (230) comprises a pump with controllable stroke frequency.
[15]
An HC dosing system according to any one of claims 12-14, comprising: - a valve configuration (288) arranged at a downstream side of the dosing unit (250).
[16]
An HC dosing system according to any one of claims 12-15, comprising: - means (200; 210; 500) adapted to substantially lower the pressure of said fuel at said dosing unit (250). 36
[17]
An HC dosing system according to any one of claims 12-16, comprising: 1. means (200; 210; 500) adapted to lower the pressure of said fuel at said dosing unit (250) steplessly.
[18]
An HC dosing system according to any one of claims 12-16, comprising: - means (200; 210; 500) adapted to lower the pressure of said branch in steps.
[19]
An HC dosing system according to any one of claims 12 to 18, comprising: 1. means (274) adapted to direct said fuel from said pressurizing means (230) to said container (205) past said dosing unit (250).
[20]
An HC dosing system according to any one of claims 12-19, comprising: 1. a feeding means (300) arranged downstream of the dosing unit (250).
[21]
A motor vehicle (100; 110) comprising an HC dosing system according to any one of claims 12-20.
[22]
A motor vehicle (100; 110) according to claim 21, wherein the motor vehicle is nAgot of a truck, bus or passenger car.
[23]
Computer program (P) in an HC dosing system for purifying exhaust gases from an engine, said computer program (P) includes program code for causing an electronic control unit (200; 500) or another computer (210; 500) connected to the electronic control unit (200; 500) to perform the steps according to any one of claims 1-11.
[24]
A computer program product comprising a program code stored on a computer readable medium for performing the steps of any of claims 1-11, when said program code is crossed on an electronic control unit (200; 500) or another computer (210; 500) connected to the electronic control unit (200; 500). 1/6 100 0 (112
类似技术:
公开号 | 公开日 | 专利标题
SE538193C2|2016-03-29|SCR system and procedure of an SCR system
JP2013531170A|2013-08-01|Method and liquid supply system related to the removal of air from a liquid supply system
SE1050648A1|2011-12-22|Method of SCR system and device of SCR system
SE537640C2|2015-09-01|Procedure for an SCR system and an SCR system
SE535631C2|2012-10-23|Procedure for the presence of air in an HC dosing system and corresponding HC dosing system
SE1350272A1|2014-09-12|Process of an HC dosing system and an HC dosing system
SE1050653A1|2011-12-22|Method and apparatus for determining the minimum level of a reducing agent container in an SCR system based on the cooling needs of a dosing unit
SE537643C2|2015-09-08|Method and apparatus for cooling an HC dosing unit for exhaust gas purification
EP2582932B1|2017-08-30|Method and device pertaining to cooling of dosing units of hc dosing systems for exhaust cleaning
SE539631C2|2017-10-24|Device and method of reducing unwanted emissions from said engine when starting an engine
SE1250265A1|2013-09-21|Procedure for an SCR system and an SCR system
SE535931C2|2013-02-26|Method and apparatus for avoiding overheating of a dosing unit in an HC dosing system
SE536895C2|2014-10-21|HC dosing system for exhaust gas purification and method of cooling thereof
WO2013089626A1|2013-06-20|Method for regulating pressure in a hc-dosing system
SE1050652A1|2011-12-22|Method of HC dosing system and device of HC dosing system
EP2627526B1|2019-12-11|Arrangement and method for controlling a ventilation system
WO2015072918A1|2015-05-21|Method and system at cold start of a motor vehicle
SE1350622A1|2014-11-23|Method and apparatus for streamlining engine operation of a motor vehicle
SE1450606A1|2014-11-22|Device and method of an exhaust gas cleaning system for an engine
GB2560502A|2018-09-19|A gasoline engine exhaust gas aftertreatment system
SE536240C2|2013-07-16|Method of HC dosing with pressure control on the basis of a temperature at exhaust pipes
SE537851C2|2015-11-03|Method of initiating dosing of reducing agent in an SCR system and an SCR system
SE1150093A1|2011-12-12|Apparatus and method for regenerating an HC dosing system
SE531257E|2016-08-08|Methods and apparatus for regenerating particulate filters and vehicles
同族专利:
公开号 | 公开日
WO2014137272A1|2014-09-12|
SE537641C2|2015-09-01|
引用文献:
公开号 | 申请日 | 公开日 | 申请人 | 专利标题

US5709080A|1996-03-15|1998-01-20|Caterpillar Inc.|Leak detection method and apparatus for an exhaust purification system|
EP1992397B1|2007-05-16|2011-09-07|Amminex A/S|Method and device for safe storage and use of volatile ammonia storage materials|
DE102008010073B4|2008-02-19|2010-10-21|Thomas Magnete Gmbh|System and method for metering a fluid|
DE102008000932A1|2008-04-02|2009-10-08|Robert Bosch Gmbh|Device for dosing a liquid reducing agent|
EP2204555B1|2009-01-02|2011-08-03|Sensirion AG|Ammonia storage system|
US8409515B2|2009-07-14|2013-04-02|GM Global Technology Operations LLC|Exhaust gas treatment system|
法律状态:
2016-11-01| NUG| Patent has lapsed|
优先权:
申请号 | 申请日 | 专利标题
SE1350272A|SE537641C2|2013-03-07|2013-03-07|Process of an HC dosing system and an HC dosing system|SE1350272A| SE537641C2|2013-03-07|2013-03-07|Process of an HC dosing system and an HC dosing system|
PCT/SE2014/050252| WO2014137272A1|2013-03-07|2014-03-03|Method pertaining to an hc dosing system and an hc dosing system|
[返回顶部]