专利摘要:
A method of filling tanks (1) with pressurized gas via a filling station (100) comprising a plurality of storage containers (2, 3, 4, 15, 16) and a fluid transfer circuit (5) since containers to the tanks (1), the circuit (5) comprising a first end to which are connected in parallel the containers (2, 3, 4, 15, 16) and a second end provided with a pipe (6) transfer intended to be connected to the tank (s) (1) to be filled, the circuit (5) comprising, arranged in series between the first end and the second end, a first isolation valve (7), a body ( 8), a second isolation valve (11), the method comprising a filling of a first reservoir (1), characterized in that at the end of the filling of the first reservoir (1). and before filling a second tank, the first (7) and second (11) isolation valves are closed to trap a reserve of gas under pressure in the circuit (5) between these two valves (7, 11) and in that, the gas supply is used to refill the at least containers
公开号:FR3033866A1
申请号:FR1552188
申请日:2015-03-17
公开日:2016-09-23
发明作者:Guillaume Roberge;Reals Guy De;Jean-Marie Verghade
申请人:Air Liquide SA;LAir Liquide SA pour lEtude et lExploitation des Procedes Georges Claude;
IPC主号:
专利说明:

[0001] The present invention relates to a method and a device for filling tanks with pressurized gas. The invention relates more particularly to a method for filling tanks with pressurized gas, in particular hydrogen under pressure, via a filling station comprising a plurality of pressurized gas storage containers and a fluid transfer circuit for the gas from containers to the tanks by pressure equalization (s), the circuit comprising a first end to which the containers are connected in parallel and a second end provided with a transfer line for detachably connected to the (x) tank ( s) to fill, the circuit comprising, arranged in series between the first end and the second end, a first isolation valve, a flow control or pressure regulator, and a second isolation valve, the method comprising a filling a first tank. The invention is advantageously applicable to fast filling (a few minutes) of hydrogen tanks under pressure (between 200 and 1000 bar for example). The invention is particularly applicable to the filling of fuel tanks of vehicles. When filling a hydrogen tank with gas under pressure, the compression of the gas in the tank produces a heating that can exceed the limits of use of the materials of the tank. To optimize these fillings a known technique consists in filling the tanks "cascade", that is to say by performing successive pressure balancing between the tank to fill and containers of pressurized gas at increasing pressures. This filling can also be completed and / or assisted by a compressor. The gas can also be cooled during filling. The documents FR2928716A1 and FR2919375A1 describe two non-limiting examples of such filling processes. There is continued interest in improving the efficiency and costs of such filling stations. An object of the present invention is to overcome all or part of the disadvantages of the prior art noted above.
[0002] For this purpose, the method according to the invention, which moreover conforms to the generic definition given in the preamble above, is essentially characterized in that, at the end of the filling of the first reservoir and before the filling of the a second reservoir, the first and second isolation valves are closed to trap a pressurized gas supply in the circuit (5) between these two valves and in that the gas supply is used to re-fill the at least containers. The present invention proposes an arrangement and / or use of filling devices to improve the efficiency of the fills.
[0003] Indeed, at the end of a completed filling, instead of evacuating the gas present in the lines of the filling circuit (discharge to the atmosphere for example), the invention retains this gas under pressure to return it. in the source containers. Furthermore, embodiments of the invention may include one or more of the following features: - the gas supply is used to fill the at least of the containers by pressure equalization, - the gas reserve is used to fill several successive pressure balancing containers, the containers being successively filled in order of decreasing pressure, i.e. by balancing the gas reserve first with the container having the highest pressure lower than the pressure of the gas reserve, then equilibrating the gas reserve with another container having a lower and lower pressure than the pressure of the gas reserve, ending with a pressure equalization between the gas reserve 25 and the container having the lowest pressure and less than the pressure of the gas reserve, - the method comprises pressure measurements within the reserve of gas and within the containers, the successive pressure balances are made in response to said pressure measurements, the gas trapped between the two isolation valves is in the conditions of temperature and pressure corresponding to the last filling phase of the first reservoir, the gas trapped between the two isolation valves has a pressure of between 200 and 1000 bar and preferably between 400 and 700 bar and a temperature of between -40 ° C. and + 85 ° C. ( according to, for example, the rate of withdrawal of the gas, the number of tanks filled, the ambient temperature, etc.) and preferably between room temperature increased by 20 ° C. and ambient temperature minus 20 ° C., the first valve of insulation is disposed near the first end of the circuit, that is to say that the first isolation valve is closer to the first end of the circuit than the second end The second isolation valve is disposed near the second end of the circuit, i.e. the second isolation valve is closer to the second end of the circuit than the first. end of the circuit, the volume of the circuit situated between the first and second isolation valves is between three and fifty liters, the length of the circuit between the first and second isolation valves is between one and five meters. hundred meters and preferably between one and one hundred meters, - at least between the first and second isolation valves the circuit comprises one or pipes comprising a thermal insulation.
[0004] The invention also relates to a device for filling tanks with pressurized gas, in particular hydrogen under pressure, comprising a filling station comprising a plurality of pressurized gas storage containers connected in parallel, via a set of respective valves. at the first end of a fluid transfer circuit of the gas from the containers to the tanks, the circuit comprising a second end provided with a transfer line for detachably connected to the tank (s) to fill, the circuit comprising, arranged in series between the first end and the second end, a first isolation valve, a flow or pressure regulator, and a second isolation valve, the circuit 30 comprising a set sensor (s) for measuring the pressure in the containers and in the circuit, the device comprising an electronic storage device and data processing connected to the sensors and valves to control the opening of the valves as a function of pressure measurements 3033866 4 of the sensors control the valves in order to achieve a tank filling (s) by successive pressure balancing with the containers, characterized in that the electronic storage, acquisition and data processing connected device is configured, at the end of the filling of a first tank and before the filling of a second tank, to control the closure first and second isolation valves for trapping a supply of pressurized gas in the circuit between these two valves and for using this gas supply to refill the at least one of the containers. According to other possible particularities, the electronic storage, acquisition and data processing connected element is configured to refill several containers with the gas reserve by successive pressure balancing in a descending order of pressure, that is, balancing the gas reserve first with the container having the higher pressure lower than the pressure of the gas supply, then balancing the gas reserve with another container having a higher pressure. lower pressure but higher than the pressure of the gas reserve, ending with a pressure equalization between the gas reserve and the container having the lowest pressure and lower than the pressure of the gas reserve. The invention may also relate to any alternative device or method comprising any combination of the above or below features. Other features and advantages will appear on reading the description below, with reference to the single figure which shows, schematically and partially, an example of a gas filling station that can implement the invention.
[0005] The device for filling tanks 1 with pressurized gas, in particular pressurized hydrogen illustrated in FIG. 1, comprises a plurality of pressurized gas storage containers 2, 3, 4, 15, 16 connected in parallel via a a set of respective valves 12, 13, 14, 17, 18, 19, 20, 21, 22, 23, at the first end of a fluidic gas transfer circuit from the containers 30 to the tanks 1 to be filled. The containers 2, 3, 4, 15, 16 store gas under pressure (for example hydrogen) at different pressures, for example between 100 and 1000 bar. The circuit 5 comprises in particular at least one fluid line.
[0006] In the example shown, five containers 2, 3, 4, 15, 16 are connected in parallel with the first end of the filling circuit 5. For example, each container 2, 3, 4, 15, 16 is connected to the first end of the circuit 5 via two respective valves arranged in series.
[0007] Conventionally, each container 2, 3, 4, 15, 16 may be provided with a respective sensor 124, 125, 126, 127, 128 for measuring the pressure within the container. As shown, each pressure sensor 124 to 128 may be located on the circuit 5 between the two series valves connected to each container. The two series valves at the outlet of each container 2, 3, 4, 15, 16 may be automatic valves used "head-to-tail". These valves may be of the electromagnetically controlled type (for example, valves in the downstream-upstream direction, if the downstream pressure is greater than the upstream pressure). In the case for example where one of the valves is sealed in both directions of circulation, one of the two valves in series can be omitted.
[0008] Likewise, each container 2, 3, 4, 15, 16 may comprise a respective temperature sensor 24 to 28 for measuring the temperature of the container and / or the gas in the container. In addition, conventionally also, each container 2, 3, 4, 15, 16 may comprise a safety device for evacuating the contents in the event of overpressure or overheating depending on the type of bottle (pressure-sensitive discharge valve) and / or at the temperature). Downstream (towards the second end), the circuit 5 may comprise for example: a first isolation valve 7, pressure sensors 30 (and possibly temperature, a calibrated orifice, a pressure control valve 8 and / or flow rate and a second isolation valve 11.
[0009] Downstream, the circuit may comprise a hose provided with a connection intended to be connected sealingly to the tank 1 to be filled. The circuit 5 may comprise an electronic control member 31 for storing, acquiring and processing data connected to the sensors and the valves to control the opening of the valves as a function of the pressure measurements of the sensors. The electronic member 31 may comprise a computer, a microprocessor, a computer or any suitable electronic logic.
[0010] Normally the control member 31 is configured (programmed or programmable) to be able to fill the reservoir (s) 1 by successive pressure balancing with the containers 2, 3, 4, 15, 16 (filling type " cascade ").
[0011] According to an advantageous feature, the control member 31 is also configured, at the end of the filling of a first tank 1 and before the filling of a second following tank, to control the closing of the first and second isolation valves. 7, 11 to trap a pressurized gas reserve in the circuit 5 between these two valves 7, 11 and to use this gas reserve to return this gas to the 2, 3, 4, 15, 16. that is to say that the residual gas of the circuit which is at the conditions (pressure in particular) of the last filling phase (last pressure equalization) can be used to fill the container or containers 2, 3, 4, 15, 16 by pressure balancing.
[0012] Preferably, the gas supply is used to fill several containers 2, 3, 4, 15, 16 by successive pressure balancing. The containers 2, 3, 4, 15, 16 are, for example, successively filled in order of decreasing pressure, that is to say by balancing the gas reserve first with the container 2, 3, 4, 15, 16 having the highest pressure lower than the gas reserve pressure, then equilibrating the gas reserve with another vessel having a lower and lower pressure than the gas reserve pressure, etc. ending with a pressure equalization between the gas reserve and the container having the lowest pressure and lower than the pressure of the gas reserve.
[0013] The successive pressure equalizations are realized for example automatically in response to said pressure measurements pressure measurements 30, 124 to 128 within the gas reserve and within the containers 2, 3, 4, 15, 16. Depending on the the gas trapped between the circuit can have a pressure of between 200 and 1000 bar and preferably between 400 and 700 bar and a temperature of between minus 40 ° C. and more than 85 ° C. (according to, for example, rate of withdrawal of the gas, the number of tanks filled, the ambient temperature, etc.) and preferably between room temperature increased by 20 ° C. and room temperature minus 20 ° C. The volume of the circuit located between the first 7 and second 11 isolation valves can be between three and fifty liters. For example, the length of the circuit 5 (conduit (s) between the first 7 and second 11 isolation valves may be from one meter to several hundred meters and preferably from one to one hundred meters. simple and inexpensive structure, the invention makes it possible to increase the utilization rate of pressurized gas containers.
[0014] Indeed, this solution does not require any structural modification of the stations of the prior art (valves and pressure sensors are already present on the installation). Only a modification of the programming or the use of the station is necessary (flow of gas in opposite direction). As shown, an additional automatic valve 29 may be provided in a parallel bypass of a residual pressure valve 32 in the circuit 5, to allow the "reverse cascade" and to vent the containers at atmospheric pressure in case of maintenance. . In addition, the connection connection of each container must be in both directions for filling and withdrawal.
[0015] The inventors have shown that the efficiency gains are significant (up to 20% more than the gas utilization rate of the containers). Indeed, this method makes it possible to improve the use rate of the containers, that is to say, to increase the quantity of gas transferred to the vehicle tanks, by making it possible to increase the number of fillings that are actually full. (that is to say at a filling rate of the vehicle greater than 95% for example). In addition, the invention makes it possible to reduce the changes of source containers (control of a set of full containers). Indeed, the invention makes it possible to avoid premature container changes by using the latter more completely. This reduces the cost of the whole. The invention can be applied to any stationary or mobile filling station and in particular to any station using mobile trailers of pressure vessels (pressure between 200 bar and 700 bar, for example for "trailer" multi compartments). For example, the set surrounded by dashed lines on the left side of the figure (containers and valves ...) may constitute the gas supply, for example 5 integral with a mobile semitrailer. The entity surrounded by dotted lines on the left of the figure may be typically the mobile tank to fill, for example integral with a vehicle. Finally, the part between these two entities (line with regulator 8 and orifice calibrated if necessary ...) can be installed in a warehouse, for example to form the relatively fixed part of the filling station. The station may comprise a compressor used in filling the tanks or containers (to supplement or complete these fills). In particular, the reserve gas can serve as a source of gas for the compressor. 15
权利要求:
Claims (12)
[0001]
REVENDICATIONS1. Method of filling tanks (1) with pressurized gas, in particular hydrogen under pressure, via a filling station (100) comprising a plurality of pressurized gas storage containers (2, 3, 4, 15, 16) and a fluid circuit (5) for transferring the gas from the containers to the tanks (1) by pressure equalization (s), the circuit (5) comprising a first end to which the containers (2, 3, 4, 15, 16) and a second end provided with a transfer line (6) intended to be removably connected to the reservoir (s) (1) to be filled, the circuit (5) comprising, arranged in series between the first end and the second end, a first isolation valve (7), a flow or pressure regulating member (8), and a second isolation valve (11), the method comprising a filling a first reservoir (1), characterized in that at the end of filling the first reservoir tank (1) and before filling a second tank, the first (7) and second (11) isolation valves are closed to trap a reserve of gas under pressure in the circuit (5) between these two valves (7). 11) and that the gas supply is used to refill at least the containers (2, 3, 4, 15, 16).
[0002]
2. Method according to claim 1, characterized in that the gas reserve is used to fill at least the containers (2, 3, 4, 15, 16) by pressure equalization.
[0003]
3. Method according to claim 1 or 2, characterized in that the gas supply is used to fill several containers (2, 3, 4, 15, 16) by successive pressure equalization, the containers (2, 3, 4, 15, 16) being successively filled in decreasing order of pressure, i.e. by balancing the gas reserve first with the container (2, 3, 4, 15, 16) having the highest pressure lower than the pressure of the gas reserve, then balancing the gas reserve with another container having a lower pressure and lower than the pressure of the gas reserve, ending with a pressure equalization between the gas reserve and the gas reserve. container 3033866 10 having the lowest pressure and lower than the pressure of the gas reserve.
[0004]
4. Method according to claim 3, characterized in that it comprises pressure measurements (30, 124 to 128) within the gas reserve and within the containers (2, 3, 4, 15, 16). and in that the successive pressure balances are made in response to said pressure measurements.
[0005]
5. Method according to any one of claims 1 to 4, characterized in that the gas trapped between the two valves (7, 11) of insulation is in the conditions of temperature and pressure 10 corresponding to the last phase of filling of the first tank (1).
[0006]
6. Method according to any one of claims 1 to 5, characterized in that the gas trapped between the two isolation valves (7, 11) has a pressure of between 200 and 1000 bar and preferably between 400 and 700 bar and a temperature between -40 ° C and 15 + 85 ° C (according to for example the rate of withdrawal of the gas, the number of tanks filled, the ambient temperature ...) and preferably between room temperature increased by 20 ° C and the ambient temperature minus 20 ° C.
[0007]
7. Method according to any one of claims 1 to 6, characterized in that the first isolation valve (7) is disposed near the first end of the circuit (5), that is to say that the first isolation valve (7) is closer to the first end of the circuit (5) than to the second end of the circuit (5).
[0008]
8. Method according to any one of claims 1 to 7, characterized in that the second isolation valve (11) is arranged close to the second end of the circuit (5), that is to say that the second isolation valve (11) is closer to the second end of the circuit (5) than to the first end of the circuit.
[0009]
9. Method according to any one of claims 1 to 8, characterized in that the volume of the circuit located between the first (7) and second (11) isolation valves is between three and fifty liters.
[0010]
10. Method according to any one of claims 1 to 9, characterized in that the length of the circuit (5) between the first (7) and 3033866 11 second (11) isolation valves is between one meter and five- hundred meters and preferably between one and a hundred meters.
[0011]
11. Device for filling tanks (1) with pressurized gas, in particular hydrogen under pressure, comprising a filling station (100) comprising a plurality of storage containers (2, 3, 4, 15, 16) pressurized gases connected in parallel, via a set of respective valves (12, 13, 14, 17, 18, 19, 20, 21, 22, 23), at the first end of a fluid transfer circuit (5) of the gas from the containers to the tanks (1), the circuit (5) comprising a second end provided with a transfer line (6) to be removably connected to the (x) tank (s) (1) fill, the circuit (5) comprising, arranged in series between the first end and the second end, a first valve (7) insulation, a member (8) for regulating flow or pressure, and a second valve (11). ), the circuit (5) comprising a set of sensor (s) (30, 124 to 128)) for measuring the pressure in the receivers. ents (2, 3, 4, 15, 16) and in the circuit (5), the device comprising an electronic member (31) for storing, acquiring and processing data connected to the sensors and the valves for controlling the opening of the valves according to the pressure measurements of the sensors control the valves in order to fill the reservoir (s) (1) by successive pressure balancing with the containers, characterized in that the electronic member (31) of storage, acquisition and processing of connected data is configured, at the end of filling a first tank (1) and before filling a second tank, to control the closing of the first and second 25 isolation valves (7, 11) for trapping a reserve of gas under pressure in the circuit (5) between these two valves (7, 11) and for using this gas reserve to refill the at least one of the containers (2, 3). , 4, 15, 16).
[0012]
12. Device according to claim 11, characterized in that the electronic member (31) for storage, acquisition and data processing 30 connected is configured to refill several containers (2, 3, 4, 15, 16 ) with the gas reserve by successive pressure equalization in a descending order of pressure, that is by balancing the gas reserve first with the container (2, 3, 4, 15, 16) having the highest pressure is lower than the pressure of the gas reserve, then balancing the gas reserve with another vessel having a lower but higher pressure than the pressure of the gas reserve, ending with a balancing pressure between the gas supply and the container having the lowest pressure and less than the pressure of the gas supply.
类似技术:
公开号 | 公开日 | 专利标题
FR3033866A1|2016-09-23|METHOD AND DEVICE FOR FILLING TANKS
CA2635970C|2015-03-31|Method and device for filling pressure gas containers
EP2191190B1|2011-10-12|Method for filling a pressurised gas container
EP3271637B1|2019-04-03|Method for filling tanks with pressurised gas
CA2751136A1|2010-08-26|Method and apparatus for filling a tank with a cryogenic liquid
CA2918366A1|2015-01-22|Device for cleaning the pipes of the drinking water circuit of an aircraft
WO2016181057A1|2016-11-17|Method and device for filling or withdrawing from a pressurized gas tank
CN102918682B|2015-06-03|Device for supplying electrolyte solution
FR2865018A1|2005-07-15|Station for filling liquid carbon dioxide to a mobile tank
EP2683948B1|2019-05-08|Equipment comprising at least one hydropneumatic accumulator with automated maintenance
WO2016162626A1|2016-10-13|Station and method for filling a tank with a fuel gas
FR2989147A1|2013-10-11|METHOD AND DEVICE FOR FILLING A PRESSURE GAS TANK
EP2823213B1|2017-04-19|Method for determining start conditions when refueling a gas tank
WO2015118261A1|2015-08-13|Method for supplying a hydrogen gas distribution station at constant pressure, and associated station
EP3702661A1|2020-09-02|Method and device for filling pressurised gas tanks
FR3090811A1|2020-06-26|Assembly for filling a liquid oxygen tank of a submarine and method of filling it
FR2947538A1|2011-01-07|FUEL STORAGE APPARATUS AND METHOD
FR3101930A1|2021-04-16|Management system of a Liquefied Natural Gas | tank for vehicle or mobile unit.
FR3068957A1|2019-01-18|TANK COMPRISING A LAUNDERING DEVICE
WO2021233964A1|2021-11-25|Device and method for transferring cryogenic fluid
FR3109201A1|2021-10-15|Device for filling pressurized gas tanks
WO2020115393A1|2020-06-11|Cryogenic fluid storage tank and method for filling same
FR3010742A1|2015-03-20|HYDRAULIC DEVICE WITH COMBINED HIGH PRESSURE AND LOW PRESSURE ACCUMULATORS FOR A HYDRAULIC MACHINE
同族专利:
公开号 | 公开日
EP3271636B1|2021-04-14|
US10591112B2|2020-03-17|
WO2016146913A1|2016-09-22|
JP2018508000A|2018-03-22|
FR3033866B1|2017-03-10|
US20180073679A1|2018-03-15|
DK3271636T3|2021-07-05|
KR20170126950A|2017-11-20|
EP3271636A1|2018-01-24|
JP6768687B2|2020-10-14|
引用文献:
公开号 | 申请日 | 公开日 | 申请人 | 专利标题
FR2928716A1|2008-03-11|2009-09-18|Air Liquide|DEVICE AND METHOD FOR FILLING A PRESSURIZED GAS IN A RESERVOIR|
US20140263420A1|2013-03-15|2014-09-18|Bpc Acquisition Company|Cng dispenser|FR3091572A1|2019-01-09|2020-07-10|L'air Liquide, Societe Anonyme Pour L'etude Et L'exploitation Des Procedes Georges Claude|Device and method for filling pressurized gas tanks|
US10711947B2|2018-06-04|2020-07-14|L'Air Liquide, Société Anonyme pour l'Etude et l'Exploitation des Procédés Georges Claude|Device for supplying pressurized fluid|
FR3093160A1|2019-02-26|2020-08-28|L'air Liquide, Societe Anonyme Pour L'etude Et L'exploitation Des Procedes Georges Claude|Method and device for filling tanks with pressurized gas.|
WO2020193922A1|2019-03-27|2020-10-01|Mcphy Energy|Filling station for supplying a plurality of vehicles with a gas containing hydrogen|US5211021A|1991-02-28|1993-05-18|Pierson Robert M|Apparatus for rapidly filling pressure vessels with gas|
US5603360A|1995-05-30|1997-02-18|Teel; James R.|Method and system for transporting natural gas from a pipeline to a compressed natural gas automotive re-fueling station|
US5868176A|1997-05-27|1999-02-09|Gas Research Institute|System for controlling the fill of compressed natural gas cylinders|
JP2003336795A|2002-03-13|2003-11-28|Nippon Sanso Corp|Fuel filling device and method for detecting fuel leakage|
AU2003266493A1|2002-09-25|2004-05-04|Taiyo Nippon Sanso Corporation|Apparatus and method for filling a fuel tank with a compressed gas like hydrogen by controlling flow and temperature|
US6786245B1|2003-02-21|2004-09-07|Air Products And Chemicals, Inc.|Self-contained mobile fueling station|
US7059364B2|2004-02-12|2006-06-13|Gas Technology Institute|Control method for high-pressure hydrogen vehicle fueling station dispensers|
US8122918B2|2005-08-31|2012-02-28|Honda Motor Co. Ltd.|Pressure differential system for controlling high pressure refill gas flow into on board vehicle fuel tanks|
JP4753696B2|2005-11-29|2011-08-24|本田技研工業株式会社|Hydrogen filling device|
US7568507B2|2005-12-06|2009-08-04|Air Products And Chemicals, Inc.|Diagnostic method and apparatus for a pressurized gas supply system|
FR2896028B1|2006-01-06|2008-07-04|Air Liquide|METHOD AND DEVICE FOR FILLING GAS CONTAINERS UNDER PRESSURE|
JP4913427B2|2006-03-10|2012-04-11|大陽日酸株式会社|Method and apparatus for filling hydrogen gas|
KR20100015355A|2007-03-02|2010-02-12|에너씨 트랜스포트 엘엘씨|Apparatus and method for flowing compressed fluids into and out of containment|
FR2919375B1|2007-07-23|2009-10-09|Air Liquide|METHOD FOR FILLING A PRESSURIZED GAS IN A RESERVOIR|
JP5525188B2|2009-06-09|2014-06-18|本田技研工業株式会社|Hydrogen filling apparatus and hydrogen filling method|
NO332687B1|2009-10-21|2012-12-10|Nel Hydrogen As|Procedure for operation and control of gas filling|
JP5328617B2|2009-11-18|2013-10-30|トヨタ自動車株式会社|Gas filling system, gas filling method, vehicle|
US9618158B2|2011-05-02|2017-04-11|New Gas Industries, L.L.C.|Method and apparatus for compressing gas in a plurality of stages to a storage tank array having a plurality of storage tanks|
JP5746962B2|2011-12-20|2015-07-08|株式会社神戸製鋼所|Gas supply method and gas supply apparatus|
US20140130938A1|2012-11-15|2014-05-15|Michael J. Luparello|Natural gas home fast fill refueling station|
DE102012023329A1|2012-11-29|2014-06-05|Linde Aktiengesellschaft|Method for performing a pressure and leak test|
FR3008165B1|2013-07-05|2017-10-27|Air Liquide|METHOD AND STATION FOR FILLING A GAS TANK|
US9541236B2|2013-07-12|2017-01-10|Whirlpool Corporation|Multi-stage home refueling appliance and method for supplying compressed natural gas|
FR3033867B1|2015-03-17|2018-06-29|L'air Liquide, Societe Anonyme Pour L'etude Et L'exploitation Des Procedes Georges Claude|METHOD FOR FILLING RESERVOIRS WITH PRESSURIZED GAS|
US10551001B2|2015-09-03|2020-02-04|J-W Power Company|Flow control system|
US10240721B2|2015-10-08|2019-03-26|Oneh2, Inc.|Method, apparatus, and system for refueling hydrogen vehicles|
FR3067094B1|2017-06-01|2020-08-14|L'air Liquide Sa Pour L'etude Et L'exploitation Des Procedes Georges Claude|TAP, STORAGE AND FILLING STATION|DE102016220259A1|2016-10-17|2018-04-19|Robert Bosch Gmbh|Method for operating a tank system|
US10241481B2|2017-03-17|2019-03-26|Fisher Controls International Llc|Methods and apparatus for controlling multiple valves as a single valve based on a coordinated control signal|
CN110553142B|2019-08-19|2021-07-02|沈军|Hydrogenation station|
法律状态:
2016-03-21| PLFP| Fee payment|Year of fee payment: 2 |
2016-09-23| PLSC| Search report ready|Effective date: 20160923 |
2017-03-22| PLFP| Fee payment|Year of fee payment: 3 |
2018-03-23| PLFP| Fee payment|Year of fee payment: 4 |
2020-03-19| PLFP| Fee payment|Year of fee payment: 6 |
2021-03-23| PLFP| Fee payment|Year of fee payment: 7 |
优先权:
申请号 | 申请日 | 专利标题
FR1552188A|FR3033866B1|2015-03-17|2015-03-17|METHOD AND DEVICE FOR FILLING TANKS|FR1552188A| FR3033866B1|2015-03-17|2015-03-17|METHOD AND DEVICE FOR FILLING TANKS|
JP2017547486A| JP6768687B2|2015-03-17|2016-02-24|How and equipment to fill the tank|
KR1020177027204A| KR20170126950A|2015-03-17|2016-02-24|Method and apparatus for filling tank|
US15/558,798| US10591112B2|2015-03-17|2016-02-24|Process and device for filling tanks|
DK16712953.5T| DK3271636T3|2015-03-17|2016-02-24|PROCEDURE AND DEVICE FOR FILLING TANK|
PCT/FR2016/050425| WO2016146913A1|2015-03-17|2016-02-24|Method and device for filling tanks|
EP16712953.5A| EP3271636B1|2015-03-17|2016-02-24|Method and device for filling tanks|