专利摘要:
METHOD TO PRODUCE A RAILWAY WITH SLAB In order to produce a railroad with slab for railway vehicles with an emergency passage (12) for road vehicles, a section of prefabricated railroad with rails (8) and sleepers (5) it is supported and positioned on a substructure (1) by means of a support and alignment device (4). Subsequently, a railroad slab (10) is produced by casting in sleepers (5). The part of the sleepers (5) that protrudes from the rail slab (10) and the rails (8) are separated by formwork elements, and an emergency passage (12) is applied to the rail slab (10 ) by casting.
公开号:BR112013016308B1
申请号:R112013016308-9
申请日:2011-12-23
公开日:2020-07-07
发明作者:Peter Laborenz;Bruno Kiefer;Anabel Hengelmann
申请人:Sonneville Ag;
IPC主号:
专利说明:

[001] The invention relates to a method for producing a rail track with slab for railway vehicles with an emergency passage for rail vehicles in which a section of the prefabricated rail track with rails and sleepers is supported and positioned on a substructure by means of a support and alignment device and a rail slab is produced by casting in the sleepers.
[002] Railways with flagstone for railway vehicles are known in the art and are preferably used in tunnels. In order to ensure rapid rescue in the event of accidents and disturbances, such railways are provided, particularly in tunnels, with emergency passages that are actionable for road vehicles and, of course, also accessible to pedestrians. A requirement with respect to the latter is that stumbling points are eliminated as far as possible.
[003] The known emergency passages consist of prefabricated slabs, for example, of concrete, resting on a concrete slab of the concrete track in which the sleepers blocks are embedded. In the case of railways with elasticly supported, vertically mobile sleepers, an additional requirement is that the emergency crossing plates do not prevent the mobility of sleepers. An advantage of these emergency passages is that the dimensions and weight of the prefabricated plates can be designed so that the plates can be transported and extended by conventional means. However, a disadvantage is that the dimensions of the slabs have to be adapted to the gauge, the dimensions of the sleepers blocks, the spacing of the sleepers blocks, and the slope of the slab of the filling concrete railroad. A slope is required to drain the water. All of these variable parameters become uneconomical to maintain a stock of prefabricated slabs. Another disadvantage of emergency passages of this type is that the plates often do not rest steadily on the slab of the concrete filling rail, so the passing vehicles cause a tilting movement and the plates are thus subjected to high wear local.
[004] On the basis of this prior art, the objective of the invention is to provide a method for producing a rail track with slab for railway vehicles with an emergency passage for road vehicles that is simple and cost effective to implement and that results in a rail track with a slab provided with a positionally stable emergency passage having a high load capacity.
[005] According to the invention, this objective is achieved in that the part of the sleepers that protrudes from the rail slab and the rails are separated by formwork elements and an emergency passage is applied to the rail slab by casting.
[006] In particular, this method offers the advantage that the emergency passage fits precisely on the rail slab and rests on it steadily. In addition, the need to prefabricate, and more particularly, maintain a stock of slabs for the emergency passage is eliminated.
[007] According to a method modality, the formwork elements are attached before the rail slab is fused. This modus operandi provides the advantage that it is not necessary to step on the rail slab to attach the formwork elements after melting the rail slab and that the emergency passage can possibly be applied before the rail slab have completely hardened.
[008] According to another method modality, the support and alignment device is removed before the emergency passage is fused. This has the advantage that no part or trace of the support and alignment device remains in the emergency passage.
[009] The invention also relates to a railroad with a slab produced according to the method of the invention.
[0010] In a rail-slab type modality, a drainage tube is arranged in the substructure and communicates with the substructure surface through connection openings provided in the substructure at determined intervals. A substructure prepared in this way eliminates the need for the subsequent installation of a drainage system.
[0011] According to another modality, the rail slab is provided with connection openings that communicate with the connection openings provided in the substructure. It is very simple to provide the rail slab with such connection openings, for example, by inserting the formed parts before the rail slab is fused.
[0012] According to another modality, the emergency passage is divided by joints extending substantially transversely to the rails. These joints absorb the expansions and contractions of the emergency passage. In addition, this allows easy step-by-step fabrication of the emergency passage according to the length of the prefabricated rail sections.
[0013] According to another modality, the emergency passage is provided with drainage shafts that communicate with the connection openings of the rail slab. These drainage shafts are preferably arranged in the area of the joints and ensure the drainage of water from the emergency passage.
[0014] If, according to another modality, the surface of the emergency passage is provided with drainage channels, the drainage of the emergency passage is further improved.
[0015] According to another modality, the sleepers have a raised shoulder on at least one side of the track whose surface is at least approximately level with the surface of the emergency passage. In this way, gaps in the emergency passage that may otherwise remain after removing the formwork elements are largely closed.
[0016] The invention still relates to formwork elements to implement the method of the invention. The main purpose of these elements is to allow quick adjustment and removal.
[0017] According to the invention, this objective is achieved in that the formwork elements consist of hoods that are intended to be fitted over parts of the sleepers and plates connecting the adjacent hoods. These hoods and plates are quickly assembled and dismountable and are, in addition, reusable.
[0018] According to a form of the formwork elements, the plates are removably connectable to the hoods. This measure also facilitates the assembly and disassembly of the formwork elements.
[0019] According to another form of formwork elements, the plates are connectable to the hoods so that the spacing between the adjacent hoods is variable. This eliminates the need to provide plates of different lengths according to the different spacing of the sleepers.
[0020] The exemplary embodiments of the invention will be described in more detail below by way of examples with reference to the accompanying drawings. The latter show:
[0021] Figures 1 to 6 six steps of a method according to the invention in the respective sectional views taken transversely to the direction of travel,
[0022] Figure 7 is a perspective view of a pair of formwork hoods,
[0023] Figure 8 is a perspective view of a rail section with adjusted and interconnected formwork hoods, and
[0024] Figure 9 is a perspective view of a section of a track with a slab according to the invention.
[0025] In Figure 1, the initial situation in a modality of the method according to the invention is illustrated by way of example. A section of railway track consisting of a plurality of sleepers 5 and tracks 8 mounted on it is supported and aligned on a substructure 1, for example, of reinforced concrete, by means of a support device and of alignment 4. In the substructure, a drainage tube 2 extends which communicates with the upper side of the substructure 1 through the connection openings 3 arranged at specified intervals. In order to cushion the vibrations produced later when the vehicles are passing over the railroad, a respective rubber shoe 6, on which an elastic insert 7 is arranged, is fitted on the bottom of each block of sleepers 5. As shown in the figure, the sleepers blocks 5 are provided on both sides of the rail 8 with projections projecting upwards 24 whose upper surfaces are accessible for walking or can be activated by road vehicles later on the finished railroad . The invention, however, is not limited to a railroad including sleepers 5 of this type.
[0026] In the illustration according to Figure 2, a respective formwork cap 9 is fitted over each block of ties 5 whose purpose is to prevent concrete access to the blocks of ties 5 and branches 8 during the subsequent casting of an emergency pass 12 (Figure 5). As another measure, before casting the slab of the rail track 10, the placement of the formwork elements may possibly be required in the area of the lateral edges of the substructure. These formwork elements may consist of known formwork panels and are not shown in the Figures.
[0027] Figure 3 shows the situation after the casting of the rail track 10, which may, for example, consist of unreinforced concrete. Basically, the formwork hoods 9 can be adjusted after casting the rail slab 10 as well. However, adjusting them beforehand, as shown in the Figures, offers the advantage that it is not necessary to step on the rail slab 10 to adjust the formwork hoods 9. The rail slab 10 has cone openings Connection 11 for drainage, which are arranged at determined intervals and aligned with the connection openings 3 mentioned with reference to Figure 1. The connection openings 11 can be obtained in a known way by inserting the corresponding parts.
[0028] Figure 4 differs from Figure 3 only in that the support and alignment device 4 was removed in the stage according to Figure 4. Starting from the situation described in Figure 4, an emergency passage 12 can now be fused as illustrated in Figure 5. Unreinforced concrete can be used for emergency passage 12 as well.
[0029] Figure 6 shows the condition of the rail track after the removal of the formwork hoods. Crosswise to the railway, the emergency passage 10 is divided into blocks, and a joint is arranged between two respective blocks of the emergency passage, as will be clearer below in the description of Figure 9. The drainage shafts 23 are arranged between two respective blocks of the emergency passage and aligned with the underlying connection openings 11.
[0030] In addition, it is clearly visible in Figure 6 that the ridges 24 of the sleepers blocks 5 are flush with the surface 25 of the emergency passage 12. Thus, the gaps as they can remain in the emergency passage 12 in the case of conventional sleeper blocks without high lugs after the removal of the formwork hoods, they are closed by the lugs 24 to an extent where the risk of accidents is greatly eliminated.
[0031] Figure 7 shows a pair of formwork hoods 9 in a perspective view. Each formwork hood 9 has two side walls 13, 15, a rear wall 14, and a top wall 16 and is open on the side facing rail 8. On both side walls 13, 15, the pieces 17 with the nut screws 18 are arranged, which are intended to fix a connection plate 19 (Figure 8). The formwork hoods 9 can consist of sheet metal, synthetic material, wood, or other suitable material. To allow the formwork hoods 9 to be removed by adjusting them outside after the concrete in the emergency passage 12 has hardened, they are slightly tapered in shape. This means that the side walls 13, 15 and the rear wall 14 are inclined about 3 degrees from the vertical so that the formwork hood tapers from the top to the bottom.
[0032] Figure 8 shows a section of a track 8 with three sleepers blocks 5 covered with formwork hoods 9. Also visible in this Figure are the connection plates 19 each connecting two respective formwork hoods 9. To fix the connection plates 19 to the connection parts 17 of the cooling hoods 9, the connection plates 19 are provided with openings 20 in which bolts 18 provided on the connection parts 17 engage. The connection plates 19 serve to prevent the concrete from the emergency passage 12 from reaching the track 8 while it is still in the fluid state. With respect to connection plates 19, different forms of formwork hoods 9 can be contemplated. Thus, instead of the connecting pieces 17, grooves can be provided on the side walls 13, 15 of the formwork hoods 9, into which the connecting plates 19 can be inserted. Also, two short connecting pieces can form an elongated gap between them, which has the same function as the grooves. Alternatively, the connection plates 19 can be permanently connected to the respective formwork hoods 9 and extend to the adjacent formwork hoods 9.
[0033] Figure 9 shows a perspective view of a section of railroad. From the bottom to the top, substructure 1, the rail slab 10, and the emergency passage 12 are visible. It is also clearly visible that a gap is left between the emergency passage 12 and the sleepers blocks 5 and the rails 8. The shoulders 24 of the sleepers blocks 5 are substantially flush with the surface of the emergency passage 12 so that no opening greater remains in the emergency passage at these locations, which may result in a risk of accidents particularly for pedestrians. Between two respective sections of the emergency passage is a joint 21, and a drainage channel 22 extends centrally between the tracks 8 in parallel to the last one. Between the two respective sections of the emergency passage 12, a vertical drainage shaft 23 is formed within which the drainage channel is opened. The drain shaft 23 is connected to the drain pipe 2 connecting connection openings 3 and 11 (see, for example, Figure 6). LIST OF REFERENCE NUMBERS 1 substructure 2 drain tube 3 connection opening 4 support and alignment device 5 sleepers block 6 rubber shoe 7 inlay 8 rail 9 formwork hood 10 rail slab 11 connection opening 12 emergency 13 side wall 14 rear wall 15 side wall 16 top wall 17 connection piece 18 screw with nut 19 connection plate 20 opening 21 gasket 22 drain channel 23 drain shaft 24 projections 5 25 surface 12
权利要求:
Claims (10)
[0001]
1. Method for producing a rail track with a slab for railway vehicles with an emergency passage for road vehicles, in which a section of prefabricated rail track with rails (8) and sleepers (5) is supported and positioned on a substructure (1) by means of a support and alignment device (4), and a rail slab (10) is produced by casting in sleepers (5), in which formwork elements (9, 19) are installed, which separate the part of the sleepers (5) that protrude from the railroad slab (10) and the rails (8), in which the formwork elements (9, 19) are provided with formwork hoods ( 9) to be coupled over parts of the sleepers (5) and, in which the emergency passage (12) is applied to the rail slab (10) by casting, characterized by the fact that a rubber shoe (6) , in which an elastic inlay (7) is arranged, is fitted on the bottom of the sleepers blocks (5), before the emergency passage is fused, and in that the formwork elements (9, 19) comprise removable plates (19) connecting the formwork hoods (9) and formwork hoods (9) adjacent, and are removed after the emergency passage (12) be applied, such that the emergency passage (12) leaves a space towards the sleepers blocks (5) and the tracks (8).
[0002]
2. Method, according to claim 1, characterized by the fact that the formwork elements (9, 19) are attached before the rail slab (10) is cast.
[0003]
Method according to any one of the preceding claims, characterized in that the support and alignment device (4) is removed before the emergency passage (12) is cast.
[0004]
4. Method, according to claim 3, characterized by the fact that a drain pipe (2) is arranged on the substructure (1) and communicates with the surface of the substructure (1) through connection openings (3) provided on the substructure (1) at specified intervals.
[0005]
5. Method, according to claim 4, characterized by the fact that the rail slab (10) is provided with connection openings (11) that communicate with the connection openings (3) provided in the substructure (1) .
[0006]
6. Method, according to any of the preceding claims, characterized by the fact that the emergency passage (12) is divided by the joints (21) extending substantially and transversely to the tracks (8).
[0007]
Method according to any one of claims 4 to 6, characterized by the fact that the emergency passage (12) is provided with drainage shafts (23) that communicate with the connection openings (11) of the slab of the rail track (10).
[0008]
Method according to any one of claims 4 to 7, characterized in that the surface of the emergency passage (12) is provided with drainage channels (22).
[0009]
9. Method according to any of the preceding claims, characterized by the fact that at least on one side of the rail (8) the sleepers (5) have a raised shoulder (24) whose surface is at least approximately level with the surface of the emergency passage (12).
[0010]
10. Method according to any of the preceding claims, characterized by the fact that the plates (9) are connectable to the hoods (19) so that the spacing between the adjacent hoods (19) is variable.
类似技术:
公开号 | 公开日 | 专利标题
BR112013016308B1|2020-07-07|method for producing a rail track with slab
BR102013031183B1|2020-12-29|method for converting ballasted track into slab track
US3300140A|1967-01-24|Beams for railroad track structure
US4117977A|1978-10-03|Highway-railway crossing
EP1700954A2|2006-09-13|Prefabricated modular member, permanent railway for tramways and subways including said member, and process for laying the same
PT1825059E|2010-05-10|Concrete track for rail vehicles
CN107190585A|2017-09-22|A kind of cast-in-place sleeper plate-type ballastless track and its construction method
US3056555A|1962-10-02|Grade crossing
PT91848B|1995-08-09|BETAO TRANSFER FOR RAILWAYS OF DIFFERENT BITOLAS
PT1288371E|2007-05-31|Ballastlesstrack with at least one monoblock sleeper
CN206308555U|2017-07-07|A kind of novel embedded rail system of subway
WO2018185351A1|2018-10-11|Concertina slab with expansion and contraction joints having long useful life for bridge decks
JP2008127900A|2008-06-05|Concrete track slab
US8025241B2|2011-09-27|Hollow sleeper
US1814239A|1931-07-14|Concrete railroad tie
US1613850A|1927-01-11|Crossing pavement
RU2431009C2|2011-10-10|Track section and method to manufacture prefabricated concrete boards
RU2493313C1|2013-09-20|Car track on concrete base
RU2746554C1|2021-04-15|Under-rail device of a railway track and a method of laying at least one under-rail device of a railway track
US1735296A|1929-11-12|Roadbed
US1381441A|1921-06-14|Railroad-tie
US819081A|1906-05-01|Concrete road-bed for railways.
US1111889A|1914-09-29|Rail-drain for railway-tracks.
US1121421A|1914-12-15|Railway-track construction in paved streets.
US1729359A|1929-09-24|Highway grade crossing for railways
同族专利:
公开号 | 公开日
BR112013016308A2|2018-06-26|
AU2011351482B2|2017-04-13|
RU2013134990A|2015-02-10|
EP2659068A1|2013-11-06|
NO2659068T3|2018-06-30|
CA2822372A1|2012-07-05|
PE20141221A1|2014-09-12|
RU2586101C2|2016-06-10|
PL2659068T3|2018-07-31|
SG191362A1|2013-08-30|
EP2468954A1|2012-06-27|
US9157192B2|2015-10-13|
KR102011811B1|2019-08-19|
KR20140020858A|2014-02-19|
WO2012089697A1|2012-07-05|
US20130277441A1|2013-10-24|
AU2011351482A1|2013-07-11|
EP2659068B1|2018-01-31|
引用文献:
公开号 | 申请日 | 公开日 | 申请人 | 专利标题

US1745747A|1929-07-15|1930-02-04|William P Day|Roadbed construction for railways|
US4793545A|1987-07-14|1988-12-27|Construction Polymers Company|Embedded track assembly|
DE4411889A1|1994-04-07|1995-10-12|Hochtief Ag Hoch Tiefbauten|Ballastless track system for at least one railroad track and method of manufacture|
US5609294A|1995-07-21|1997-03-11|Lucas, Jr.; Joseph|Railroad track assembly and method|
FR2741090B1|1995-11-09|1998-01-30|Allevard Sa|BALLAST-FREE RAILWAY CROSSING SLIPPERS|
DE202008008157U1|2008-06-18|2009-10-29|Heilit + Woerner Bau Gmbh|Railway track, in particular for a tunnel or bridge area|
DE202009008366U1|2008-07-08|2009-08-20|Heilit+Woerner Bau Gmbh|Railway track, in particular for a tunnel or bridge area|
DE202009008365U1|2009-06-17|2010-10-28|Heilit+Woerner Bau Gmbh|Railway track, in particular for a tunnel or bridge area|
DE102010030275A1|2009-06-19|2011-03-10|Ed. Züblin Ag|Device for enabling trafficability of fixed track in railway tunnel with rubber-tired emergency vehicle, has prefabricated parts adapted to sleepers in terms of shape and creating trafficable surface filled up with concrete up to level|US9689116B2|2011-04-05|2017-06-27|Newstyle Nominees Pty Ltd.|Rail track sleeper support|
ES2649963T3|2012-12-07|2018-01-16|Sonneville Ag|Procedure to convert a track on ballast into a solid track|
EP2778284A1|2013-03-11|2014-09-17|Sonneville AG|Sleeper block unit for railway rail systems|
CN103821049B|2014-01-25|2016-08-24|中铁四局集团第四工程有限公司|A kind of CRTS II template CA mortar injection steel pipe angle steel combination edge sealing hold down gag|
EP3045588A1|2015-01-14|2016-07-20|Sonneville AG|Sealing arrangement between sleeper block and sleeper shoe of a railway rail system|
JP6407796B2|2015-05-14|2018-10-17|公益財団法人鉄道総合技術研究所|Sleeper construction method with formwork holding function|
CN106049193B|2016-05-17|2018-08-17|中国铁道科学研究院铁道建筑研究所|One kind being used for roadbed section ballastless track of high-speed railway center line method for correcting error|
CN106049204B|2016-08-03|2018-02-06|中铁十七局集团第三工程有限公司|Non-fragment orbit reinforced concrete footing is poured with groove template|
CN106245467B|2016-08-23|2017-11-24|吴永芳|A kind of paving frame method for assembling board-like track structure|
CN107460794A|2017-04-24|2017-12-12|中铁四局集团有限公司|One kind is in the plate-type non-fragment orbit precast construction methods of severe cold area CRTS III|
CN108642975B|2018-03-08|2020-01-21|中国铁路设计集团有限公司|Method for lifting settlement damaged railway roadbed|
EA036000B1|2018-06-29|2020-09-10|Открытое Акционерное Общество "Российские Железные Дороги"|Surface water drainage system for a double-track ballastless railway superstructure|
CN109778596B|2018-08-16|2019-12-10|广州地铁设计研究院股份有限公司|trapezoidal prefabricated slab with auxiliary blocks and construction method thereof|
CN109837811B|2018-12-26|2021-03-19|中国铁道科学研究院集团有限公司铁道建筑研究所|Counterforce structure for transverse deviation rectification of ballastless track of roadbed section and manufacturing method thereof|
CN110130164A|2019-04-22|2019-08-16|中铁五局集团有限公司|A kind of two groups of long sleeper buried-type crossover turnout railway roadbed casting methods|
CN110180999B|2019-06-25|2020-10-02|遵义航天新力精密铸锻有限公司|Positioning tool and method for positioning pipe fitting in sand casting cooling plate by using same|
DE202019003793U1|2019-09-13|2019-11-08|Ed. Züblin Aktiengesellschaft|Frame for a track covering for a slab track and arrangement comprising a slab track and a track covering|
CN111676742B|2020-01-13|2021-09-21|中国铁道科学研究院集团有限公司铁道建筑研究所|Deviation rectifying method for CRTS III plate type ballastless track structure|
CN112127216B|2020-09-30|2021-12-03|武汉理工大学|Prefabricated assembly type asphalt substrate type ballastless track and construction method thereof|
法律状态:
2018-12-18| B06F| Objections, documents and/or translations needed after an examination request according [chapter 6.6 patent gazette]|
2019-08-27| B06U| Preliminary requirement: requests with searches performed by other patent offices: procedure suspended [chapter 6.21 patent gazette]|
2020-05-05| B09A| Decision: intention to grant [chapter 9.1 patent gazette]|
2020-07-07| B16A| Patent or certificate of addition of invention granted [chapter 16.1 patent gazette]|Free format text: PRAZO DE VALIDADE: 20 (VINTE) ANOS CONTADOS A PARTIR DE 23/12/2011, OBSERVADAS AS CONDICOES LEGAIS. |
优先权:
申请号 | 申请日 | 专利标题
EP10197028.3|2010-12-27|
EP10197028A|EP2468954A1|2010-12-27|2010-12-27|Method for manufacturing a ballastless trackway for rail vehicles with an recue route for street vehicles|
PCT/EP2011/074024|WO2012089697A1|2010-12-27|2011-12-23|Method for producing a slab trackway|
[返回顶部]