专利摘要:
processing facility built at least in part, by coupling the first, second and third process blocks and modular construction system the various processes of a plant are segmented into separate process blocks that are connected to each other using fluid conduits or electrical connections. each process block is specialized in performing specific tasks in a manner, on the assembly line, to achieve a global objective. for example, multiple distillation process blocks can be chain-linked to create fuel from crude oil. each process block is generally small enough to be mounted on a truck or on a flat base for easy transport, allowing an assembly line of process blocks to be transported anywhere in the world with ease.
公开号:BR112012014815B1
申请号:R112012014815-0
申请日:2010-12-17
公开日:2020-01-07
发明作者:Fred Harney;Gary Donovan;Todd Roth;Alan Lowrie;George Morlidge;Simon Lucchini;Sean Halvorsen
申请人:Fluor Technologies Corporation;
IPC主号:
专利说明:

“PROCESSING INSTALLATION BUILT AT LEAST IN PART,
FOR THE FIRST, SECOND AND THIRD BLOCKS COUPLING
MODULAR CONSTRUCTION PROCESS AND SYSTEM.
[001] -This patent application claims the priority of US provisional application no. 61/287956, filed on December 18, 2009, which together with all other references deposited concurrently are incorporated herein by reference in their entirety.
[002] -The field of the invention is the modular construction of processing facilities, with particular examples given in relation to modular processing facilities for oil sands.
[003] -The construction of facilities for large-scale processing can be extraordinarily challenging in remote locations or under adverse conditions. A particular geography that is both remote and undergoes severe adverse conditions includes the terrain comprising Canada's western provinces, where several companies are now trying to establish processing plants for removing oil from tar sands.
[004] - Given the difficulties of building facilities entirely on site, there has been considerable interest in what will be called Second Generation Modular Construction. In that technology, the facilities are logically segmented into interchangeable type modules, the modules being built in an established industrial area, taken by trucks or by air to the
Petition 870190021390, of 03/01/2019, p. 21/51
2/23
place gives construction, and So there coupled. Various installations modular in Construction Modular in Monday Generation is not mounted in Sands bituminous in Alberta,
Canada, having proven the provision of several advantages in terms of assembly speed, quality of construction work, reduction in safety risks and in the total cost of the project. There is even an example of a Modular Reactor of
Helium (RMH), described in an article by Dr. Arkal Shenoy and Dr. Alexander Telengator, General Atomics, 3550 General Atomics Court, San Diego, CA 92121.
[005] -The Second Generation Modular Installations have also been described in the patent literature. An example of a large-capacity oil refinery composed of multiple self-contained and interconnected modular units is described in WO 03/031012 by Shumway. A generic Second Generation Modular Facility is described in Stanfield United States Patent 20080127662.
[006] - Unless expressly indicated here otherwise, Shumway and all other extrinsic materials discussed here, and in the descriptive report and in the priority annexes, are incorporated by reference in their entirety. When a definition or the use of a term in an embedded reference is inconsistent with or contrary to the definition that term provided in the present, the definition provided in the present of that term applies and the definition of that term in the reference does not apply.
[007] -There are significant savings when using the Second Generation Modular. Note, for example,
Petition 870190021390, of 03/01/2019, p. 22/51
3/23 that the construction of a process module costs 4 US dollars in the field for every dollar spent on the construction of an equivalent module in a construction facility. However, despite the many advantages of the Second Generation Modular, there are still problems. Possibly, the most serious problems arise from the ways in which the various modules are interconnected. In the prior art to the Second Generation Modular units, the fluid, supply and control lines are built on external pipe supports. This can be seen clearly in Figures 1 and 2 of WO 03/031012. In installations that use multiple, self-contained and substantially identical production units, it is logically simple to operate these units in parallel, and to provide supply (input) and product (output) lines along an external pipe support. But, when small production units are not practical or economical, the use of external pipe supports is an impediment.
[008] -What is needed is a new modular paradigm, where the various processes of a plant are segmented into process blocks comprising multiple modules. We refer to these projects and implementations as the Third Generation Modular Construction.
[009] -The subject of the invention provides equipment, systems and methods where the various processes of a plant are segmented into process blocks, each comprising multiple modules, in which at least some of the modules within at least some of the blocks are fluid and
Petition 870190021390, of 03/01/2019, p. 23/51
4/23 electrically coupled to at least another of the modules using direct module-to-module connections.
[010] -In the preferred embodiments, a processing facility is built at least partially by coupling three or more process blocks. Each of at least two of the blocks comprises at least two interchangeable modules, and more preferably three, four, five or even more of these modules. The contemplated embodiments can be quite large, and can have four, five, ten or even twenty or more process blocks, which collectively comprise up to one hundred, two hundred or even a greater number of interchangeable modules. All types of industrial processing facilities are included, including nuclear, gas-fired, coal-fired, or other energy-producing facilities, chemical plants and mechanical plants.
[011] -Unless the context indicates otherwise, all ranges indicated herein should be interpreted as including their measurement points, and ranges without specified deadlines should be interpreted including only commercially practical values. Similarly, all lists of values should be considered to include intermediate values, unless the context indicates otherwise.
[012] - As used herein, the term process block means a part of a processing facility that has several process systems within a distinct geographical boundary. As an example, an installation
Petition 870190021390, of 03/01/2019, p. 24/51
5/23 may have process blocks for generating electricity or steam, for distillation, for purification or for separating one material from another, for crushing, grinding, or for carrying out other mechanical operations, for carrying out reactions chemicals with or without the use of catalysts, for cooling and so on.
[013] - As used herein, the term interchangeable module means a section of a process block that includes multiple pieces of equipment, and which has a transport weight between 20,000 Kg and 200,000 Kg. The concept is that, a commercially subset viable interchangeable modules would be large enough to practically transport the necessary equipment and support structures, but it would also be suitable for transportation on highways of commercial use in a relevant geographic area, for a certain time of the year. It is contemplated that a typical interchangeable module for areas of tar sands in Western Canada would have between 30,000 Kg and 180,000 Kg, and more preferably between 40,000 Kg and 160,000 Kg. From a dimensions perspective, these modules would normally measure between 15 and 30 meters long, and at least 3 meters high and 3 meters wide, but not more than 35 meters long, 8 meters wide, and 8 meters high.
[014] - Interchangeable modules can be closed on all sides, and on the top and bottom, but more normally these modules would have at least one side open, and possibly all four sides open, as well
Petition 870190021390, of 03/01/2019, p. 25/51
6/23 as an open top. The open sides allow the modules to be positioned adjacent to each other on the open sides, thus creating a large open space, comprising 2, 3, 4, 5 or even more modules, by which an engineer could walk from one module to another within a process block.
[015] -A typical interchangeable module may well include equipment from multiple disciplines, such as process and scaffolding equipment, platforms, wiring, instrumentation and lighting.
[016] - A very significant advantage of Third Generation Modular Construction is that process blocks are designed to have a relatively small number of external couplings. In preferred embodiments, for example, there are at least two process blocks that are fluidly coupled by no more than three, four or five fluid lines, excluding utility lines. However, it is contemplated that there could be two or more process blocks that could be coupled by six, seven, eight, nine, ten or more fluid lines, excluding the utility lines. The same is contemplated in relation to the power lines, and the same is contemplated in relation to the control lines (that is, wired communications). In each of these cases, the fluid, supply and control lines, it is contemplated that a given line that enters a process block will distribute to several modules within the process block. The term distribute is not limited to a narrow literal sense, but in a
Petition 870190021390, of 03/01/2019, p. 26/51
7/23 broader sense, which includes situations in which, for example, a given fluid line divides into smaller lines that transport the fluid to different parts of the process block by means of orthogonal, parallel and other guidelines.
[017] - Process blocks can be assembled, in any suitable way. It is contemplated, for example, that process blocks can be positioned end to end and / or side by side and / or above / below each other. The facilities contemplated include those arranged in matrices of x by y blocks, where x is at least 2 and y is at least 3. Within each process block, modules can also be arranged in any suitable way despite
that, how the modules are probably a lot more long of what are wide, the blocks of process favorite has 3 or 4 modules willing to side, and touching in both or in one of your ends collective
on the sides of one or more other modules. The individual process blocks can certainly have different numbers of modules and, for example, a first process block could have five modules, another process block could have two modules, and a third process block could have two other modules. In other embodiments, a first process block could have at least five modules, another process block could have at least five other modules and a third process block could have at least five other modules.
Petition 870190021390, of 03/01/2019, p. 27/51
8/23 [018] -In some embodiments contemplated, Modular Installations of Third Generation are those in which the process blocks collectively include equipment configured to extract oil from tar sands. Also contemplated are installations in which at least one of the process blocks produces the energy used by at least one other process block, and independently, in which at least one of the process blocks produces steam used by at least one other process block, and independently, in which at least one of the process blocks includes a cooling tower with at least two floors. It is also contemplated that at least one of the process blocks includes a personal control area, which is coupled in a controlled manner to at least one other process block using optical fibers. In general, but not necessarily in all cases, the process blocks of a Third Generation Modular Installation would collectively include at least one reservoir, a compressor, an exchanger, a pump, a filter.
[019] - Although a Modular Installation of Third Generation may have one or more pipe supports in order to interconnect the modules within a process block, it does not necessarily have to be so. Thus, it is contemplated that a modular construction system can comprise modules A, B, and C juxtaposed, side by side, each of the modules having (a) a height greater than 4 meters and a width greater than 4 meters, and (b) at least one open side; and a first fluid line coupling
Petition 870190021390, of 03/01/2019, p. 28/51
9/23 modules A and B; a second fluid line coupling modules B and C; and in which the first and second lines of fluids pass through an interconnection of the pre-installed process block and do not pass through a support for common interconnecting pipes.
[020] -Various objectives, characteristics, aspects and advantages of the subject of the invention will become more apparent from the following description of the exemplary embodiments and the figures in the accompanying drawings.
figure 1 is a flow chart showing some of the steps involved in the Third Generation Construction Process;
figure 2 is an example of a Third Generation Construction Process Block showing a first level grid and equipment layout;
Figure 3 is a simple layout of the Third Generation Building block;
figure 4 is a schematic of three exemplary process blocks (No. 1, No. 2 and No. 3) in an oil separation facility designed for the tar sands region of Western Canada;
figure 5 is a schematic of an elevation view of the layout of a process block module, where modules C, B and A are on one level, most likely on the ground level, with a fourth module D placed above the module C;
Petition 870190021390, of 03/01/2019, p. 29/51
10/23 figure 6 is a schematic of an alternative embodiment of a part of an oil separation plant, where again there are three process blocks (No. 1, No. 2 and No. 3);
figure 7 is a schematic of the oil treatment process block No. 1 in figure 3, showing the three modules mentioned above, plus two additional modules arranged on a second level;
figure 8 is a schematic of a Third Generation Modular Installation having four process blocks, each of which has five modules.
[021] -In one aspect of the preferred embodiments, the modular construction system would still comprise a first command line coupling modules A and B; a second command line coupling modules B and C; and in which the first and second command lines do not pass through the common pipe support. In more preferred embodiments, modules A, B, and C comprise at least 5, at least 8, at least 12, or at least 15 modules. Preferably, at least two of process blocks A, B and C are fluidly coupled by no more than five fluid lines, excluding utility lines. In yet other preferred embodiments, a module D could be stacked on top of module C, and a third fluid line could directly couple modules C and D.
[022] -The methods for the provision of a Second Generation Installation are different, in many
Petition 870190021390, of 03/01/2019, p. 30/51
11/23 aspects, of those used for the provision of a Third Generation Modular Installation. Considering that the former usually only involves the division of equipment for a given process between several modules, the latter preferably occurs in a five-step process as described below. It is contemplated that while the traditional Second Generation Modular Construction can prefabricate about 50-60% of the work of a complex, a Multi Generation Modular Construction of the Third Generation can prefabricate up to about 90-95% of the work.
[023] -Other information for the design of Third Generation Modular Construction facilities is included in the 3rd Generation Modular Execution Design Guide, which is included in this order. The Project Guide should be interpreted as exemplary of one or more preferred embodiments, and the text that indicates specificities (eg, will be or should be) should, therefore, be seen only as suggestive of one or more forms of preferred embodiments. Where the Design Guide refers to confidential software, data or other design tools, which are not included in this order, such software, data or other design tools will not be incorporated by reference. In the event of a discrepancy between the Project Guide and this report, the report will be valid.
[024] -Figure 1 is a flow chart 100 showing the steps in the production of an installation for Process of
Petition 870190021390, of 03/01/2019, p. 31/51
12/23
Third Generation Construction. In general, there are three steps, as discussed below.
[025] - Step 101 serves to identify the installation configuration for the Third Generation Construction Process using process blocks. In this step, the main process normally separates the facilities into process blocks. This is best accomplished with the development of a process block flowchart. Each process block contains a distinct set of process systems. A process block will have one or more feed streams and one or more product streams. The process block will process the feed in different products, as shown.
[026] - Step 102 is used to allocate a plot space for each Third Generation Construction Process Block. Plotting space allocation requires a piping design specialist to distribute the relevant equipment within each Third Generation Construction Process Block. In this phase of the project, only the estimated weights and dimensions of the equipment provided by the process / mechanical sector should be used to prepare each block. An arrangement of equipment in the Third Generation Construction Process Block requires attention to the location in order to guarantee the effective integration of the pipeline distribution, electrical and control parts. To provide guidance to the project specialist, the steps must be followed:
Petition 870190021390, of 03/01/2019, p. 32/51
13/23 [027] - Step 102A is used to obtain the types, sizes and weights required for the equipment. It is important that the equipment is dimensioned so that it can be effectively adapted to a module. Any equipment that has been dimensioned and that cannot be effectively adapted to the module envelope must be evaluated by the main process for possible resizing for the effective installation of the module.
[028] - Step 102B serves to establish a total geometric area for the process block using a combination of transportable module dimensions. A first and a second level must be identified using a grid design, where the grid identifies each module limit within the process block.
[029] - Step 102C serves to allocate space for the electrical distribution and control panels on the first level. Figure 2 is an example of a first level grid and equipment layout in the Third Generation Construction Process Block. The E&I panels are dimensioned to include the motor control centers and the distributed instrument and I / O controllers necessary to energize and control the equipment, instrumentation, lighting and electrical heating layout within the process block. The module containing the E&I panels is referred to as the Third Generation primary process block module. Consult the E&I installation details for the Third Generation module projects.
Petition 870190021390, of 03/01/2019, p. 33/51
14/23 [030] - Step 102D serves to group equipment and instruments by primary systems using the
Process block DFPs.
[031] - Step 102E serves to distribute each group of equipment per system in the process block layout, ensuring that the equipment does not exceed the limits of the module. The layout should focus on keeping the pumps located on the same grid and module level as the E&I distribution panels. This will assist in maintaining the household electrical power cables together. If not practical, the second best arrangement would be to have the pumps or any other motor close to the module with the E&I distribution panels. In addition, the equipment must be spaced to ensure operational effectiveness, maintenance capacity and safe access and egress.
[032] -The use of Fluor's Optimeyes® is an effective tool at this stage of the project to help in the disposition of the process block.
[033] -Stage 103 serves to prepare a detailed disposition of the equipment inside the Process Blocks for the production of an integrated Third Generation installation. Each process block identified in step 2 is established in a plot space, ensuring that the necessary interconnections between the blocks are minimized. Primary interconnections are identified from the Process Flow Block diagram. The supports for traditional interconnecting tubes are not
Petition 870190021390, of 03/01/2019, p. 34/51
15/23 preferably more needed or used. Piping paths are integrated into the module. A simple and typical Third Generation block layout is illustrated in figure 3.
[034] -Stage 104 is used to develop a Third Generation Module Configuration Table and a power distribution and control plan, which combines process blocks for the entire installation in order to eliminate the traditional interconnection supports for tubes and reduce the number of interconnections. The Third Generation Module Configuration Table is developed using the data above. Models can be used, and, for example, a Third Generation power distribution and control plan can be advantageously prepared using the architectural model for Third Generation power distribution and control.
[035] - Step 105 serves to develop a Third Generation modular plan, which includes fully detailed process block modules on integrated multidisciplinary bases. The final step in this phase of a project is to prepare a general modular plan for Third Generation Modular Execution, which can be used to establish the baselines to proceed to the next phase. It is contemplated that a Third Generation Modular Execution will require a different schedule than the modular projects traditionally executed.
[036] -Many of the differences between
Modular First and Second Generation Buildings
Petition 870190021390, of 03/01/2019, p. 35/51
16/23
Generation and Third Generation Modular Construction are set out in Table 1 below, with references to the
Project for Modular Execution of Third Generation, which was deposited with the original provisional order:
Activities Modular Execution Modular Third Party ExecutionGeneration Interchangeable Traditional Definition of The steps are: Use worker process Disposition and 1. Develop a plan in structured to develop the Module Plot using dimensions plot layout withof equipment and based on the development ofDiagrams of Flow in Process Blocks withProcesses (DFPs). Optimize equipment, pipes,the interconnections between electrical andequipment. fully instrumentation2. Develop Limits in integrated, includingmodules using the plan in following steps:Plotting and the Envelope in 1. Identify the configurationModule Transport.installation process3. Develop provisions Third Generation using blocksdetailed modules and processes using DFPs.interconnections in between the 2. Allocate a spacemodules and parts plotting for each block ofbuilt from installations Third Generation process.using a network in 3. Detailed arrangement ofsupportsin equipment inside the Blockspipes / support the in process using methodologynumb and supports Third Generation for
Petition 870190021390, of 03/01/2019, p. 36/51
17/23
Activities Modular ExecutionTraditional Interchangeable Modular Third Party ExecutionGenerationvaried. eliminate traditional support4. Route the cabling for pipeselectrical and controls interconnection and minimize orfor the support of reduce interconnectionsinterconnection and supports inside the modules of thevaried to connect several Process.loads and instruments with The provision sets out thesupports and substations Based Process Blockssatellites. in the modular blocks thatNote: This results in a fit the envelope ofcombination of modules transport.first generation (supports 4. Combine the Blockspipes) and Installation processsecond generation (supports general to eliminateof pipes with traditional mediaselected equipment) interconnection for pipes andthat fit the envelope reduce the number ofcarriage. interconnections.Ref .: Section 1.4 A 5. Develop an action plan Modular Third Party Construction Generation, which includes fully process block detailed on base integrated multidisciplinary approach. Note: This results in a plot layout
Petition 870190021390, of 03/01/2019, p. 37/51
18/23
Activities Modular ExecutionTraditional Interchangeable Modular Third Party ExecutionGeneration fully integrated completely built from the Module blocks that fit the shipping envelope.Ref .: Sections 2.2 to 2.4 Supports Pipe and tube supports Eliminates traditional for sleepers supports pipe supports and supports tubes / supports modulated, including of modular sleepers. At of sleepers cable tray for interconnections are integratedinstallation in the field in the modules of theinterconnections and cables processes for installation indomestic. workshop.Ref .: Section 2.5 Ref .: Section 2.2 Buildings Multiple constructions Buildings are integratedstandalone designed and in modules ofpre-built based Process.in discreet equipment housings. Ref .: Section 3.3D Architecture • Distribution • Decentralized MCC and gives centralized and MCC in apparatus integrated with Distribution main substations and Localized process blocks power by satellite. in the Blocks module• Feeders Primary Processes.household individual • Feeders for
Petition 870190021390, of 03/01/2019, p. 38/51
19/23
Activities Modular ExecutionTraditional Interchangeable Modular Third Party ExecutionGenerationleave substations s by loads are directed Fromsatellite for drivers and Decentralized MCCs and givesloads through From localized equipment at theinterlocks connection Process block without Thefor tubes.need for supports in• Cabling in interconnection for tubes. power installed and 0 cabling for Thefinalized on the site.energy distribution is installed and finished at modules workshop for The Block interconnection in process with the connectors in prefinished cables, OR wrapped around the module boundary for interconnection on the site in intermodular feeders for loads inside From Process blocks using pre-wired cable connectors finalized. Ref .: Section 3.3EInstruments • Cabinets in • Control cabinets and systems control are central ized are decentralized and of control in substations for integrated into the Block modulesatellites or distri buido Primary Process Management. randomly in • Close the coupling From
Petition 870190021390, of 03/01/2019, p. 39/51
20/23
Activities Modular ExecutionTraditional Interchangeable Modular Third Party ExecutionGenerationprocess facilitiesinstruments for locating mock• Locations From all instruments for oneinstruments are out single module system inmechanical and mechanical Process block up to the limitof the pipes.as much as possible. • The majority of • 0 cabling givescabling From instrumentation is installed andinstruments and gives finished in the workshop ofcheckout is done at the module. The interconnections offield for multiple Process Block moduleintermodular boundaries and use pre-wound cabling andbuilt parts per pre-installed at the limit ofcable tray middle module for connecting to the uncleor various supports using cable connectorsinstalled on the brackets in pre-finalized. pipe interconnectionRef .: Section 3.3F
TABLE 1 [037] - Figure 4 is a schematic (plan view) of three exemplary process blocks (No. 1, No. 2 and No. 3) in an oil separation facility designed for the oil sands region of the Western Canada. Here, process block no. 1 has two modules (no. Len ° 2), process block no. 2 has two modules (no. 3 and no. 4), and process block no. 3 has only one module (No. 5). The dotted lines between the modules indicate the open sides of adjacent modules, whereas the solid lines at the
Petition 870190021390, of 03/01/2019, p. 40/51
21/23 around the modules indicate walls. The arrows show fluid and electrical couplings between the modules. Thus, Drawing 1 shows only two, a power line connection and a fluid line connection between modules # 1 and # 2. Similarly, Drawing 1 does not show electrical line connections between process blocks # 1 and 2, and only a single fluid line connection between those process blocks.
[038] -Figure 5 is a schematic of an elevation view of the process block module layout, where modules C, B and A are on one level, most likely the ground level, with a fourth module D placed above module C. Although only two fluid couplings are shown, the Drawing should be understood as potentially including one or more other fluid couplings, and one or more electrical and control couplings.
[039] - Figure 6 is a schematic of an alternative embodiment of a part of an oil separation facility, where there are again three process blocks (No. 1, No. 2 and No. 3). But here, process block # 1 has three modules (# 1, # 2 and # 3), process block # 2 has two modules (# 1 and # 2), and the process block No. 3 has two other modules (No. 1 and No. 2).
[040] -Figure 7 is a diagram of block No. 1 of the oil treatment process in Figure 3, showing the three modules mentioned above, plus two other modules placed on a second level.
Petition 870190021390, of 03/01/2019, p. 41/51
22/23 [041] -Figure 8 is a schematic of a Modular Installation of Third Generation having four process blocks, each having five modules. Although the dimensions are not shown, each of the modules must be interpreted as having (a) a length of at least 15 meters, (b) a height greater than 4 meters, (c) a width greater than 4 meters, and (d) having open sides and / or ends in which the modules within a given process block are positioned adjacent to each other. In this particular example, the first and second process blocks are fluidly coupled by no more than four fluid lines, excluding utility lines, four electrical lines, and two control lines. The first and third process blocks are connected by six fluid lines, excluding utility lines, and by an electric line and a control line.
[042] -Also in figure 8, it is distributed an primary electrical power source from the block in processes 1 for four of the block's five modules in process 3, and the process block control line 1 and distributed for all five of the block modules in process 3. [043] -Must be apparent to technicians at the subject that several other modifications are possible besides of those already described without abandoning the concepts of the invention
presented. The subject of the invention, therefore, should not be restricted except for the appended claims. Besides that,
Petition 870190021390, of 03/01/2019, p. 42/51
23/23 in the interpretation of both the specifications and the claims, all terms must be interpreted in the broadest possible way consistent with the context. In particular, the terms understand and comprise should be interpreted as referring to elements, components, or steps in a non-exclusive way, indicating that the referenced elements, components or steps may be present, or used, or combined with other elements, components or steps that are not expressly referenced. Where the claims in the report refer to at least one component of something selected from the
group consisting of A, B, C ... and N, the text should to be interpreted as need only an element of group, and not the most N, or B plus N, etc.
Petition 870190021390, of 03/01/2019, p. 43/51
权利要求:
Claims (16)
[1]
1. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, BY THE FIRST, SECOND AND THIRD PROCESS BLOCK COUPLING”, characterized by the fact that at least t modules that can be transported by truck are used to collectively compose the process blocks, where t is at least five, and where each of the t modules (A, B, C) is fluid and electrically coupled to at least one other of the t modules (A, B, C), using direct module connection a module, in which the first process block is configured to carry out a first process, and includes at least a first module (A, B, C) and a second module (A, B, C), and the second process block it is configured to run a second process different from the first process, and includes at least a third module (A, B, C) and a fourth module (A, B, C);
at what fur one less module includes an interconnection block process pre-installed for to less at one within a line of fluid, a line in power and an line of control, and where any less one module and at least, one fluid line out of, one line in power and an line of control are configured to
allow at least one of a fluid line, a supply line and a control line, to be distributed to another module within the process block, where the first module (A, B, C) is in contiguity with the third module (A, B, C) along the open sides, so that an open space is created to cross between the first module (A, B, C) and the
Petition 870190105903, of 10/18/2019, p. 16/21
[2]
2/5 third module (A, B, C).
2. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, THROUGH THE FIRST, SECOND AND THIRD PROCESS BLOCKS”, according to claim 1, characterized by the fact that at least three of the modules (A, B, C) have :
(a) a height greater than 4 meters and a width greater than 4 meters, and (b) at least one open side.
[3]
3. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, THROUGH THE FIRST, SECOND AND THIRD PROCESS BLOCKS”, according to claim 1, characterized by the fact that the first and the second process blocks are fluidly coupled by no more than 5 fluid lines, excluding utility lines.
[4]
4. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, BY COUPLING THE FIRST, SECOND AND THIRD PROCESS BLOCKS”, according to claim 3, characterized by the fact that the first and second process blocks are fluidly coupled by no more than 5 power lines.
[5]
5. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, THROUGH THE FIRST, SECOND AND THIRD PROCESS BLOCKS”, according to claim 1, characterized by the fact that the first and third process blocks are fluidly coupled by at least five fluid lines, excluding utility lines.
Petition 870190105903, of 10/18/2019, p. 17/21
3/5
[6]
6. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, THROUGH THE FIRST, SECOND AND THIRD PROCESS BLOCKS”, according to claim 1, characterized by the fact that the first process block is positioned adjacent to each of the second and the third process block.
[7]
7. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, THROUGH THE FIRST, SECOND AND THIRD PROCESS BLOCKS”, according to claim 1, characterized by the fact that t is at least ten, in which the first process block includes at least five among the modules (A, B, C), that the second process block includes at least two among the modules (A, B, C) and the third process block includes at least two among the modules the modules (A, B, C).
[8]
8. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, THROUGH THE FIRST, SECOND AND THIRD PROCESS BLOCKS”, according to claim 1, characterized by the fact that each of the t modules (A, B, C) is at least 15 meters long.
[9]
9. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, THROUGH THE FIRST, SECOND AND THIRD PROCESS BLOCKS”, according to claim 1, characterized by the fact that the process blocks collectively include equipment configured to extract oil from sand bituminous.
[10]
10. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, BY COUPLING OF FIRST, SECOND AND
Petition 870190105903, of 10/18/2019, p. 18/21
4/5
THIRD PROCESS BLOCKS ”, according to the claim
1, characterized by the fact that at least one of the process blocks produces energy used by at least one other of the process blocks.
[11]
11. “BUILDING PROCESSING INSTALLATION
AT LEAST IN PART, THROUGH THE FIRST, SECOND AND THIRD PROCESS BLOCKS ”, according to claim 1, characterized by the fact that at least one of the process blocks produces steam used by at least one other among process blocks.
[12]
12. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, BY THE FIRST, SECOND AND THIRD THIRD PROCESS BLOCKS”, according to claim 1, characterized by the fact that at least one of the process blocks includes at least one tower two-story cooling unit.
[13]
13. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, BY THE FIRST, SECOND AND THIRD PROCESS BLOCKS”, according to claim 1, characterized by the fact that a primary electrical power source is distributed to several modules ( A, B, C) within a process block.
[14]
14. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, THROUGH THE FIRST, SECOND AND THIRD PROCESS BLOCKS”, according to claim 1, characterized by the fact that a control line is distributed to several modules (A, B, C) within a process block.
Petition 870190105903, of 10/18/2019, p. 19/21
5/5
[15]
15. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, THROUGH THE FIRST, SECOND AND THIRD PROCESS BLOCKS”, according to claim 1, characterized by the fact that at least one of the process blocks includes a control area personnel, and the control is coupled to at least one other among the process blocks using optical fibers.
[16]
16. “PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, THROUGH THE FIRST, SECOND AND THIRD PROCESS BLOCKS”, according to claim 1, characterized by the fact that the process blocks collectively include at least one among a reservoir, a compressor, an exchanger, a pump and a filter.
类似技术:
公开号 | 公开日 | 专利标题
BR112012014815B1|2020-01-07|PROCESSING INSTALLATION CONSTRUCTED AT LEAST IN PART, BY FIRST, SECOND AND THIRD THIRD PARTY BLOCKS AND MODULAR CONSTRUCTION SYSTEM
US20170159305A1|2017-06-08|Modular processing facility
CN105451504A|2016-03-30|Machine room, data center, and data center system
Sultan et al.2019|Evaluation of the impact of high penetration levels of PV power plants on the capacity, frequency and voltage stability of Egypt’s unified grid
AU2014202657B2|2016-07-07|Modular processing facility
CN106529740A|2017-03-22|Natural gas network, power network and power supply combined planning method
WO2018144204A1|2018-08-09|Modular processing facility with distributed cooling systems
EP3419761A1|2019-01-02|Modular processing facility
Buitrago-Velandia et al.2021|Dynamic reactive power compensation in power systems through the optimal siting and sizing of photovoltaic sources
Jin et al.2012|A practical protection coordination strategy applied to secondary and facility microgrids
CA3011563A1|2017-08-10|Modular systems and methods for developing gas fields
US20210180862A1|2021-06-17|Cracker modular processing facility
Duong et al.2019|Combination of K-Mean clustering and elbow technique in mitigating losses of distribution network
JP6621335B2|2019-12-18|Nuclear power plant and 3D-CAD system for design
Hudișteanu et al.2021|Enhancement of PV Panel Power Production by Passive Cooling Using Heat Sinks with Perforated Fins
CN110402314B|2021-04-13|Metal structure for supporting fluid conduit and industrial equipment having the same
CN207251111U|2018-04-17|A kind of large span communication cable crane span structure
JP6292395B2|2018-03-14|Waste heat recovery boiler and method for assembling the same
Bedair2021|Structural design guidelines for Delayed Coker Unit | used in hydrocarbon industry
Kim et al.2021|Analysis of Induced Voltage on Pipeline Located Close to Parallel Distribution System
Bandel et al.2002|Working the kinks out of piping design: minimize change orders by accounting for a multitude of details at the design stage.|
Galindo-García et al.2012|CFD Simulations of a Heat Recovery Steam Generator for the Aid of Power Plant Personnel
Pinedoa et al.2015|Biorefinery Process Optimization and Risk Estimation at Industrial Level
Lu et al.1983|Seismic qualification of PWR plant auxiliary feedwater systems
同族专利:
公开号 | 公开日
AU2010330872B9|2018-09-06|
CL2010001469A1|2012-04-09|
EP2516759A1|2012-10-31|
US20150143775A1|2015-05-28|
US20150292223A1|2015-10-15|
AU2010330872B2|2014-04-24|
US20110146164A1|2011-06-23|
WO2011075625A1|2011-06-23|
EP2516759B1|2020-02-12|
CA2724938C|2017-01-24|
CN106948490A|2017-07-14|
BR112012014815A2|2016-08-16|
CA2724938A1|2011-06-18|
MX337599B|2016-03-11|
US10458140B2|2019-10-29|
EP2516759A4|2014-11-05|
US8931217B2|2015-01-13|
ZA201205131B|2014-12-23|
MX2012007092A|2012-07-30|
AU2010330872A1|2012-07-05|
CN102859087A|2013-01-02|
US9376828B2|2016-06-28|
引用文献:
公开号 | 申请日 | 公开日 | 申请人 | 专利标题

US3274745A|1962-07-02|1966-09-27|Foster Wheeler Corp|Process for constructing a petroleum refinery|
US3643389A|1970-06-30|1972-02-22|Ibm|Modular electrical enclosure|
US3707165A|1970-08-10|1972-12-26|Joel S Stahl|Plastic plumbing wall|
US3925679A|1973-09-21|1975-12-09|Westinghouse Electric Corp|Modular operating centers and methods of building same for use in electric power generating plants and other industrial and commercial plants, processes and systems|
US4055050A|1976-02-11|1977-10-25|Vladimir Borisovich Kozlov|Apparatus for and method of regasifying liquefied natural gas|
US4527981A|1978-05-15|1985-07-09|Chisum Finis L|Method and apparatus for designing a log home|
GB1604759A|1978-05-31|1981-12-16|Kump E J|Space module|
US4267822A|1978-11-08|1981-05-19|Grumman Energy Systems, Inc.|Integrated solar energy system|
FR2475505A1|1980-02-08|1981-08-14|Veco Sarl|CONTAINER FOR TRANSPORTING A CHAIN OF MANUFACTURE, TREATMENT, EXPERIMENTATION, EXAMINATION OR THE LIKE|
US4457116A|1980-06-12|1984-07-03|Kump Ernest J|Space module|
FR2500525B1|1981-02-23|1985-05-03|Bretagne Atel Chantiers|
FR2563559A1|1984-04-25|1985-10-31|Wieczorek Julien|Shelters and protective systems for petroleum and petrochemical installations|
FR2638196B1|1988-10-26|1991-01-25|Roche Jean|METHOD AND DEVICE FOR MODULAR CONSTRUCTION OF INDUSTRIAL BUILDINGS|
US4992669A|1989-02-16|1991-02-12|Parmley Daniel W|Modular energy system|
DE4218615C1|1992-06-05|1993-07-15|Nukem Gmbh, 8755 Alzenau, De|
DE19837692C2|1998-08-19|2003-04-03|Bentec Gmbh Drilling & Oilfield Systems|Drilling device, drilling rig and method for drilling an exploration and production well|
US6176046B1|1998-11-24|2001-01-23|Northstar Industries, Inc.|Portable, pre-manufactured, modular natural gas delivery stations|
US6116050A|1998-12-04|2000-09-12|Ipsi Llc|Propane recovery methods|
US6716355B1|1999-05-27|2004-04-06|Nederlands Organisatie Voor Toegepast-Natuurwetenshappelijk Onderzoek Tno|Method for the purification of a liquid by membrane distillation, in particular for the production of desalinated water from seawater or brackish water or process water|
US6308465B1|1999-06-21|2001-10-30|Equitech, Inc.|Systems and utility modules for buildings|
NO312736B1|2000-02-10|2002-06-24|Sinvent As|Method and plant for cooling and possibly liquefying a product gas|
JP2001325016A|2000-05-15|2001-11-22|Denso Corp|Production method and production system|
WO2003031012A1|2001-09-14|2003-04-17|Precision Systems Engineering|Modular oil refinery|
DE10149316A1|2001-10-05|2003-04-17|Univ Albert Ludwigs Freiburg|Micro-fluid channel system, to separate solids from suspensions for on-the-chip analysis, comprises an inflow reservoir and a stretch with an elbow curve leading to at least two outflow reservoirs|
US6786051B2|2001-10-26|2004-09-07|Vulcan Advanced Mobile Power Systems, L.L.C.|Trailer mounted mobile power system|
US7051553B2|2002-05-20|2006-05-30|Floor Technologies Corporation|Twin reflux process and configurations for improved natural gas liquids recovery|
US8621786B2|2003-02-13|2014-01-07|Wei Chak Joseph Lam|Efficient layout and design of production facility|
US7264694B2|2004-01-29|2007-09-04|Oil-Tech, Inc.|Retort heating apparatus and methods|
US7255180B2|2004-05-03|2007-08-14|Drillmar, Inc.|Modular drill system requiring limited field assembly and limited equipment support|
JP4447639B2|2004-07-01|2010-04-07|オートロフ・エンジニアーズ・リミテッド|Treatment of liquefied natural gas|
US7708086B2|2004-11-19|2010-05-04|Baker Hughes Incorporated|Modular drilling apparatus with power and/or data transmission|
US7647976B2|2006-04-21|2010-01-19|Maoz Betzer Tsilevich|System and method for steam-assisted gravity drainage -based heavy oil well production|
MX2008016457A|2006-06-19|2009-07-22|Hydrokool Llc|Method, system, and apparatus for modular central plant.|
US8097451B2|2006-08-07|2012-01-17|Mark K Gaalswyk|Self-contained deployable automatic factory built ethanol production plant|
US20080178537A1|2007-01-31|2008-07-31|Spangler John M|Portable modular manufacturing system|
RU2007119695A|2007-05-28|2008-12-10|Николай Иванович Григорьев |MODULAR BOILER ROOM|
US20100024351A1|2008-07-29|2010-02-04|Green Horizon Manufacturing Llc|Method of deploying and redeploying a prefabricated structure|
US20100132390A1|2008-09-18|2010-06-03|Multistack Llc|Variable four pipe heatpump chiller|
US8157003B2|2008-12-18|2012-04-17|Stillwater Energy Group, Llc|Integrated carbon management system for petroleum refining|
US10294658B2|2008-12-23|2019-05-21|Xoma Llc|Flexible manufacturing system|
US20130066772A1|2011-09-09|2013-03-14|Chuyu Xiong|Multi-factor and multi-channel id authentication and transaction control and multi-option payment system and method|
US8535419B2|2009-04-01|2013-09-17|Zephyr Gas Services Llc|Modular amine plant|
JP5391836B2|2009-05-29|2014-01-15|株式会社日立製作所|Module structure and plant construction method|
US8070389B2|2009-06-11|2011-12-06|Technip France|Modular topsides system and method having dual installation capabilities for offshore structures|
AU2014202657B2|2009-12-18|2016-07-07|Fluor Technologies Corporation|Modular processing facility|
CA3015351A1|2016-02-26|2017-08-31|Fluor Technologies Corporation|Modular processing facility|
CA2724938C|2009-12-18|2017-01-24|Fluor Technologies Corporation|Modular processing facility|
US20170159305A1|2009-12-18|2017-06-08|Fluor Technologies Corporation|Modular processing facility|
AU2011357584A1|2011-01-28|2013-08-01|1Nsite Technologies Ltd.|Modular transportable system for SAGD process|
CA2729457C|2011-01-27|2013-08-06|Fort Hills Energy L.P.|Process for integration of paraffinic froth treatment hub and a bitumen ore mining and extraction facility|
US9670113B2|2012-07-09|2017-06-06|Siluria Technologies, Inc.|Natural gas processing and systems|
AU2012216352B2|2012-08-22|2015-02-12|Woodside Energy Technologies Pty Ltd|Modular LNG production facility|
US9701597B2|2014-01-09|2017-07-11|Siluria Technologies, Inc.|Oxidative coupling of methane implementations for olefin production|
US20170216766A1|2016-02-01|2017-08-03|Fluor Technologies Corporation|Modular systems and methods for developing gas fields|
US20180220552A1|2017-01-31|2018-08-02|Fluor Technologies Corporation|Modular processing facility with distributed cooling systems|CA2668253C|2008-06-03|2016-07-26|Richard F. Ablett|Plant waste bio-product pomace extract concentrates and processes of producing same|
CA2724938C|2009-12-18|2017-01-24|Fluor Technologies Corporation|Modular processing facility|
CA2729457C|2011-01-27|2013-08-06|Fort Hills Energy L.P.|Process for integration of paraffinic froth treatment hub and a bitumen ore mining and extraction facility|
CA2906715C|2011-02-25|2016-07-26|Fort Hills Energy L.P.|Process for treating high paraffin diluted bitumen|
CA2733342C|2011-03-01|2016-08-02|Fort Hills Energy L.P.|Process and unit for solvent recovery from solvent diluted tailings derived from bitumen froth treatment|
CA2806588C|2011-03-04|2014-12-23|Fort Hills Energy L.P.|Process for solvent addition to bitumen froth with in-line mixing and conditioning stages|
CA2735311C|2011-03-22|2013-09-24|Fort Hills Energy L.P.|Process for direct steam injection heating of oil sands bitumen froth|
CA2737410C|2011-04-15|2013-10-15|Fort Hills Energy L.P.|Heat recovery for bitumen froth treatment plant integration with sealed closed-loop cooling circuit|
CA2805804C|2011-04-28|2014-07-08|Fort Hills Energy L.P.|Process and tsru with inlet with multiple nozzle configuration for distribution of solvent diluted tailings|
CA2857702C|2011-05-04|2015-07-07|Fort Hills Energy L.P.|Process for operating a bitumen froth treatment operation in turndown mode|
CA2832269C|2011-05-18|2017-10-17|Fort Hills Energy L.P.|Temperature control of bitumen froth treatment process with trim heating of solvent streams|
US9603281B2|2012-03-12|2017-03-21|Compass Datacenters, Llc|Truly modular building datacenter facility|
AU2012216352B2|2012-08-22|2015-02-12|Woodside Energy Technologies Pty Ltd|Modular LNG production facility|
DE102013201171A1|2013-01-24|2014-07-24|Infracor Gmbh|Method and system for using an industrial property|
US9664026B2|2013-03-13|2017-05-30|Nathaniel Davis Greene|Modular system for extracting hydrocarbons from subterranean volumes and associated methods|
EP2979049A4|2013-03-27|2016-11-30|Woodside Energy Technologies Pty Ltd|Air-cooled modular lng production facility|
US20140353463A1|2013-06-04|2014-12-04|Fluor Technologies Coporation|Rotating equipment modularization|
WO2015073981A1|2013-11-18|2015-05-21|Red Flint Group, LLC|Modular batch plant for granular products|
US10240693B2|2014-02-07|2019-03-26|Private Equity Oak Lp|Detachable pipe rack module with detachable connectors for use in a processing facility|
US20180036709A1|2014-05-27|2018-02-08|Portable GTL Systems, LLC|Portable fuel synthesizer|
US9453333B2|2014-08-27|2016-09-27|Ronald Porter|System and method of fabricating and assembling industrial plant modules for industrial plant construction|
WO2016181029A1|2015-05-13|2016-11-17|OutotecOy|A flotation plant and its uses and methods of maintenance of a flotation plant|
US20170216766A1|2016-02-01|2017-08-03|Fluor Technologies Corporation|Modular systems and methods for developing gas fields|
US10822826B2|2016-12-16|2020-11-03|Unicharm Corporation|Factory for manufacturing absorbent article|
US20180220552A1|2017-01-31|2018-08-02|Fluor Technologies Corporation|Modular processing facility with distributed cooling systems|
CA3021456A1|2017-10-20|2019-04-20|Fluor Technologies Corporation|Integrated configuration for a steam assisted gravity drainage central processing facility|
US20210180862A1|2017-10-31|2021-06-17|Fluor Technologies Corporation|Cracker modular processing facility|
法律状态:
2019-01-02| B06T| Formal requirements before examination|
2019-01-08| B06F| Objections, documents and/or translations needed after an examination request according art. 34 industrial property law|
2019-07-30| B07A| Technical examination (opinion): publication of technical examination (opinion)|
2019-10-29| B09A| Decision: intention to grant|
2020-01-07| B16A| Patent or certificate of addition of invention granted|Free format text: PRAZO DE VALIDADE: 20 (VINTE) ANOS CONTADOS A PARTIR DE 17/12/2010, OBSERVADAS AS CONDICOES LEGAIS. |
优先权:
申请号 | 申请日 | 专利标题
US28795609P| true| 2009-12-18|2009-12-18|
US61/287,956|2009-12-18|
PCT/US2010/060969|WO2011075625A1|2009-12-18|2010-12-17|Modular processing facility|
[返回顶部]